Resource Allocation, Leveling and Smoothing

Where each lesson comes from, what was not supplied, and the places where the material needs a careful reading.

The sources

Prepared from the supplied 56-page Resource Allocation, Leveling and Smoothing.pdf and twelve-slide same-name PPTX companion by Farah Demachkieh, Ph.D., for Project Planning, Scheduling and Controls. PDF references count pages including title and dividers; PPTX references count slides independently. The detailed PDF's text, tables and image-only diagrams and the complete companion's native text, tables and diagrams were reviewed. The companion confirms the existing worker and compressor examples and adds the engineer allocation/loading example and construction RACI table. Lessons paraphrase these sources; redrawn charts, derived arithmetic, questions and reflections support study rather than reproduce an official assessment. Neither deck identifies a course week number for this topic.

Listening

Use Listen on lesson and summary pages for the same Marin AI narration as the other narrated courses, with sentence and word highlighting. Back to the lessons

Where the resource-planning lessons come from
LessonSource coveragePDF pagesCompanion PPTX slides
1 · Resources and responsibilityResource types, WBS/OBS, RAM/RACI and engineer allocation2–9; 192–4
2 · Worker capacityRenewable network, profiles, capacity tests and lower bound10–155 (capacity recap only)
3 · Supply and loadingNon-renewable example, cumulative graph, Gantt charts and loading16–17; 22–23; 36–392 (daily loading only)
4 · Constraints and prioritiesLeveling purpose, industries, priority rules, constraints and interventions18–21; 24–35; 446
5 · Loading-chart exampleNetwork, table, early profile and split C40–43No counterpart
6 · Leveling and smoothingDefinitions, comparison, compressor inputs, revised schedules and rental decision45–557–12

Read with carePDF page 1 and companion slide 1 identify the source and author. PDF page 56 closes the detailed deck. The two source numbering systems are separate; the complete companion is covered above.

Lesson 01

Identify resources and assign responsibility

Resource planning connects the work to the people, equipment, materials and funding it needs. Start by distinguishing resource types, then use the WBS, OBS and responsibility matrix to make ownership clear.

Open the lesson
Companion allocation and responsibility recap

The eight-hour engineer assigned ten hours, three resource types with crew/steel/generator examples, and the construction RACI table.

Companion PPTX slides 2–4
Capacity and resource types

Over-allocation and renewable, non-renewable and doubly constrained resources; labor, equipment and materials.

PDF pp. 2–4 and 19
Work and ownership

OBS, its intersection with the WBS, the responsibility matrix and departmental examples.

PDF pp. 5–7
Roles and legends

RACI definitions, the symbol legend, and the conflict between prose and graphic for the Gain user buy-in assignments.

PDF pp. 8–9

Lesson 02

Test worker capacity before trusting a finish date

The five-activity example requires 101 worker-weeks and has nine workers available per week. Its twelve-week network schedule passes a total-capacity check but overloads individual weeks. Follow the early and late schedules, then interpret the duration bound carefully.

Open the lesson
Inputs and initial feasibility

Five-activity network, nine-worker limit, 101 worker-weeks and the W ≤ DR condition.

PDF pp. 10–11
Early and late loading

Activity timing, weekly demand, cumulative work and idle capacity; the late table covers weeks 9–12, although its prose mentions only 9 and 10.

PDF pp. 12–13
Refined test and duration bound

The displayed twelve-week arithmetic, the inconsistent eight-week question, and D ≥ 112/9.

PDF pp. 14–15
Companion capacity recap

The same 101 worker-weeks, 108 worker-weeks of aggregate capacity and week-five demand of fourteen against nine available. The summary does not repeat the PDF's refined lower-bound calculation.

Companion PPTX slide 5

Lesson 03

Read cumulative supply and load the schedule

Finite resources need to arrive before they are consumed. Compare cumulative supply with cumulative requirements, then connect resources to the time-phased baseline so conflicts become visible before execution.

Open the lesson
Finite resources and their supply

Example 2 activity table and graphical cumulative supply/requirement comparison.

PDF pp. 16–17
Gantt charts and resource loading

Gantt-chart uses, MS Project illustrations, loading definition and planning benefits.

PDF pp. 22–23 and 36–39
Companion loading example

The engineer's simultaneous six- and four-hour assignments illustrate daily loading against an eight-hour limit.

Companion PPTX slide 2

Lesson 04

Choose priorities that respect the project constraints

A fixed deadline, a fixed resource pool and a project with both limits call for different trade-offs. Use the deck's five priority rules as scheduling aids, then choose a practical response and check the resulting schedule again.

Open the lesson
Purpose and industry examples

Leveling objectives, combinatorial nature and applications; the broad terminology on p. 20 is distinguished later on pp. 46–47.

PDF pp. 18–21
Five priority rules

Slack, duration, identification, successors and resource demand; the ID example needs care because it supplies start dates rather than IDs.

PDF pp. 24–30
Constraints and interventions

Time, resource and mixed constraints, followed by moving, splitting, reassignment, additional resources and overtime.

PDF pp. 31–35 and 44
Companion priority guidance

Check readiness, compare float, consider the other named rules and recalculate successors and demand after a move. The companion allows activity ID to break a tie; the detailed PDF also presents it as a distinct rule.

Companion PPTX slide 6

Lesson 05

Build a loading chart and smooth it within float

Follow the six-activity loading-chart example from network dates to a resource profile. Then split C within its available float to reduce the peak from nine resource units to seven while preserving the twelve-day finish.

Open the lesson
Network and activity table

The six-activity example, early starts, late finishes, resource amounts and C's four days of slack.

PDF pp. 40–41
Initial and smoothed profiles

The initial profile is reconstructed from the network/table because p. 42 delays D, E and F inconsistently and ends at day 14. The split-C chart on p. 43 agrees with the twelve-day table. Interval totals and seventy-two resource-days are derived arithmetic.

PDF pp. 40–43

Lesson 06

Compare leveling and smoothing with six compressors

The seven-activity compressor example begins with a twenty-day critical-path schedule and six overloaded days. Leveling respects the six-compressor limit and finishes in twenty-two days. Smoothing keeps twenty days and leaves two days needing extra capacity.

Open the lesson
Distinguishing the techniques

Time-first smoothing, resource-first leveling, comparison table and house example.

PDF pp. 45–48
Original inputs and conflicts

Image-table predecessor, duration and compressor inputs, critical path, original day ranges and six overloaded days.

PDF pp. 49–52
Revised schedules

D's move, F's subsequent move, the twenty-two-day leveled result and the remaining two smoothing conflicts. The two extra compressors are calculated from eight required minus six available.

PDF pp. 53–55
Companion compressor example and decision

The same seven activity inputs and original overloads, smoothing and leveling day ranges, comparison table and two-compressor rental decision.

Companion PPTX slides 7–12

Source appendix

Where the material needs a careful reading

Read with care

Two sources share examples but serve different levels of detail

The twelve-slide PPTX is a concise companion to the 56-page PDF. It retains the worker and compressor inputs and outcomes, while adding the eight-hour engineer and clear construction RACI examples. It does not repeat the cumulative-supply, split-C or refined duration-bound material. PDF pages and PPTX slides are therefore cited separately.

Work and organizational breakdown

Page 5 attributes scope decomposition to OBS, while pages 6–7 distinguish the WBS's work breakdown from the OBS's organizational ownership. The lessons follow that clearer distinction.

The responsibility example contradicts its own graphic

Page 9's prose names Ann responsible, Dave support and Sue approval for Gain user buy-in. Its graphic instead marks Jim responsible, Sue support, Ann notification and no approver. The lessons disclose the mismatch and practice tests the unambiguous legend rather than the named assignments. Support is not automatically RACI Consulted.

The eight-week label conflicts with the arithmetic

Page 14 asks about eight weeks, but states D=12 and uses 108=12×9. The lesson calls the displayed calculation a twelve-week test. Its idle-loss units are worker-weeks.

Read both profiles, not only their prose

The early chart overloads weeks 4 and 5. The late chart overloads weeks 4–8, and its table shows two unused workers in every week from 9 through 12, although its prose mentions only weeks 9 and 10.

A bound does not establish an executable schedule

Page 15 gives D≥112/9, about 12.44 weeks. Thirteen whole weeks is a consequence of rounding the bound, not a demonstrated resource-feasible plan.

Terminology becomes more precise later

Page 20 calls leveling 'or smoothing'. Pages 46–47 explicitly distinguish resource-first leveling from time-first smoothing, including the possibility of residual smoothing conflicts. The lessons use the later distinction.

Check the priority example's actual criterion

Page 28 names lowest identification number but compares start days. The lesson preserves the ID-based rule and flags the example mismatch.

A suggested move is not a complete capacity proof

The broad construction example on p. 20 does not provide a complete feasible schedule for the five-, seven- and six-worker tasks under a ten-worker limit. The resulting overlaps still need checking.

Keep the numerical examples separate

The worker example uses weeks and a nine-worker limit. The loading chart uses elapsed days and no stated hard capacity limit. The compressor example uses inclusive days and a six-compressor limit. Their inputs and units are not interchangeable.

Splitting assumes interruptible work

Page 43 splits C into one early day and two later days. Restart costs and real execution constraints are not analyzed in the deck.

The initial loading chart disagrees with its activity table

Page 42 places D at 7–11, E at 11–13 and F at 13–14 despite the network/table on pages 40–41 giving 5–9, 9–11 and 11–12. The guide reconstructs the initial profile from the network/table, and labels that correction. Page 43's split-C chart agrees with the table. Both reconstructed profiles contain seventy-two resource-days.

Supply is graphical, and resource order can be added

The finite-supply illustration has no separate dated delivery table. In the compressor example, F originally follows C and D; E-before-F is introduced to respect resources in the leveled plan, explaining the revised controlling sequence.

Checked against the supplied documents cited in each note.

What not to take away

The lessons actively work against these misreadings:

  • Naming a responsible person proves that enough capacity is available.
  • All resources renew every period.
  • Every responsibility matrix uses the same symbols as RACI.
  • Passing W≤DR guarantees the requested finish date.
  • Early-start and late-start schedules automatically respect resource limits.
  • A duration lower bound is a demonstrated feasible schedule.
  • Enough total supply at completion means there were no earlier shortages.
  • A priority rule can override a predecessor or a hard capacity limit.
  • A high resource peak is an overload even when no availability limit is specified.
  • Smoothing reduces the total amount of required work.
  • Leveling and smoothing always produce the same finish and resource demand.
  • Keeping twenty days in the compressor example resolves all conflicts with six compressors.

Study-guide synthesis; each item is addressed in the lessons.