Two sources share examples but serve different levels of detailThe twelve-slide PPTX is a concise companion to the 56-page PDF. It retains the worker and compressor inputs and outcomes, while adding the eight-hour engineer and clear construction RACI examples. It does not repeat the cumulative-supply, split-C or refined duration-bound material. PDF pages and PPTX slides are therefore cited separately.
Work and organizational breakdownPage 5 attributes scope decomposition to OBS, while pages 6–7 distinguish the WBS's work breakdown from the OBS's organizational ownership. The lessons follow that clearer distinction.
The responsibility example contradicts its own graphicPage 9's prose names Ann responsible, Dave support and Sue approval for Gain user buy-in. Its graphic instead marks Jim responsible, Sue support, Ann notification and no approver. The lessons disclose the mismatch and practice tests the unambiguous legend rather than the named assignments. Support is not automatically RACI Consulted.
The eight-week label conflicts with the arithmeticPage 14 asks about eight weeks, but states D=12 and uses 108=12×9. The lesson calls the displayed calculation a twelve-week test. Its idle-loss units are worker-weeks.
Read both profiles, not only their proseThe early chart overloads weeks 4 and 5. The late chart overloads weeks 4–8, and its table shows two unused workers in every week from 9 through 12, although its prose mentions only weeks 9 and 10.
A bound does not establish an executable schedulePage 15 gives D≥112/9, about 12.44 weeks. Thirteen whole weeks is a consequence of rounding the bound, not a demonstrated resource-feasible plan.
Terminology becomes more precise laterPage 20 calls leveling 'or smoothing'. Pages 46–47 explicitly distinguish resource-first leveling from time-first smoothing, including the possibility of residual smoothing conflicts. The lessons use the later distinction.
Check the priority example's actual criterionPage 28 names lowest identification number but compares start days. The lesson preserves the ID-based rule and flags the example mismatch.
A suggested move is not a complete capacity proofThe broad construction example on p. 20 does not provide a complete feasible schedule for the five-, seven- and six-worker tasks under a ten-worker limit. The resulting overlaps still need checking.
Keep the numerical examples separateThe worker example uses weeks and a nine-worker limit. The loading chart uses elapsed days and no stated hard capacity limit. The compressor example uses inclusive days and a six-compressor limit. Their inputs and units are not interchangeable.
Splitting assumes interruptible workPage 43 splits C into one early day and two later days. Restart costs and real execution constraints are not analyzed in the deck.
The initial loading chart disagrees with its activity tablePage 42 places D at 7–11, E at 11–13 and F at 13–14 despite the network/table on pages 40–41 giving 5–9, 9–11 and 11–12. The guide reconstructs the initial profile from the network/table, and labels that correction. Page 43's split-C chart agrees with the table. Both reconstructed profiles contain seventy-two resource-days.
Supply is graphical, and resource order can be addedThe finite-supply illustration has no separate dated delivery table. In the compressor example, F originally follows C and D; E-before-F is introduced to respect resources in the leveled plan, explaining the revised controlling sequence.
Checked against the supplied documents cited in each note.