Planning & Controls · Resource allocationLesson 3

Study explanation · Lesson 03 · 8 min

Read cumulative supply and load the schedule

Finite resources need to arrive before they are consumed. Compare cumulative supply with cumulative requirements, then connect resources to the time-phased baseline so conflicts become visible before execution.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

A finite total must also be available at the right time

The non-renewable example has A followed by parallel B and C, then D after both. A takes six weeks and requires six units. B takes five weeks and requires twelve units. C takes three weeks and requires ten units. D takes two weeks and requires eight units. The total requirement is thirty-six units. These are quantities for each activity, not worker counts to multiply by duration. The network starts A at elapsed week zero, B and C at week six, and D at week eleven. C can start as late as week eight while keeping the network finish at thirteen. Those dates describe precedence flexibility. They do not by themselves establish when the non-renewable supply is sufficient.

Example 2 inputs and network dates, PDF p. 16
ActivityWeeksTotal unitsEarly startLate start
A6600
B51266
C31068
D281111

Read with careThe dates use elapsed weeks from zero. The units column is a finite activity requirement, not units per week.

Compare cumulative curves at every relevant date

On the source graph, the dotted curve is cumulative resources required and the solid curve is cumulative resources supplied. A shortage exists wherever cumulative requirements exceed supply. Receiving enough units eventually does not make an earlier activity executable when its needed supply was missing. The requirement curve reaches thirty-six units. The source highlights a mismatch around week nine, but the drawing also shows earlier gaps. Its solid supply curve eventually reaches forty units, exceeding the total requirement. The learning point is the timing of the gaps, rather than treating the last supply total as proof that the original schedule works. The deck provides a graphical illustration rather than a separate dated delivery table, so exact purchasing commitments should not be inferred from it.

Key ideaAt each date, cumulative consumption must fit within the cumulative supply available by that date.

Resource loading makes demand visible over time

Resource loading assigns the required amounts of resources to activities across the project baseline. It maps their use through time so the team can see overlapping claims, shortages and underutilization. The source links loading to better planning, identifying conflicts before work starts, and deciding whether additional resources are needed to make the baseline realistic. A Gantt chart provides the time-phased view of the work. The deck describes it as easy to create and understand, useful for tracking, establishing a baseline, updating progress and identifying resource needs. The MS Project screenshots show resources associated with scheduled work and time-phased hours. They illustrate a view of resource demand; the deck does not supply a complete software tutorial.

From scheduled work to a capacity check
  1. SchedulePlace activities and dependencies in time
  2. LoadAssign the required resource amounts
  3. CompareSum concurrent demand and check supply
  4. RespondRevise the plan and check again

Key takeaways

  • Non-renewable activity quantities are not automatically rates per week.
  • Compare cumulative requirements and supply throughout the schedule.
  • Resource loading connects resource demand to the baseline timeline.
  • A Gantt chart helps reveal demand; a capacity check establishes whether the demand fits.

Based on the supplied Resource Allocation, Leveling and Smoothing PDF and PPTX companion by Farah Demachkieh, Ph.D. Separate page and slide references appear in source notes; practice and reflections are study-guide additions.

Your study checkpoint

Ready to continue?

Mark the lesson complete once you have read it and tried its idea on something real.

Next · Lesson 4