Approval creates a reference for control
The session connects the approved scope to a scope baseline: an official reference point for monitoring and control. The three elements are the Scope Statement, the approved WBS and the WBS dictionary. Together they explain the agreed boundary, its breakdown and the detail behind that breakdown. A reference matters because a team cannot assess a request reliably when nobody can say what was previously agreed. The baseline makes that comparison possible. It also gives a clearer basis for discussing whether work is already included or would add to the commitment.
Scope Statement
- Detailed scope boundary
- Deliverables and acceptance criteria
- Exclusions, constraints and assumptions
Approved WBS
- Breakdown of agreed work
- Coverage of the full scope
- Manageable work packages
WBS dictionary
- Description of WBS elements
- Owners and responsibilities
- Duration, cost and resources
The dictionary explains the boxes
A hierarchy often shows an element's name without its duration, cost or other detail. The lecturer uses the WBS dictionary to explain each element, including its description, owner, duration, cost, resources and responsibilities. This supports a shared understanding beyond the visual chart. Study example: a package labeled “Testing” could mean different things to two teams. A dictionary entry can state the result to be tested, the responsible person, the work covered and the expected resources. The recording identifies the fields to describe; this guide does not present its example as an official instructor template.
| Field | Study example |
|---|---|
| Package | Registration confirmation check |
| Description | Check the agreed confirmation message and access details |
| Owner | Registration lead |
| Duration and resources | Estimated review period and assigned reviewer |
| Budget and responsibility | Agreed review allowance and responsibility for corrections |
Read with careA teaching illustration of the named information, with no invented official costs or durations.
Compare a proposal before changing the commitment
When someone requests a change, the lecturer says to compare the proposal with the approved baseline before deciding whether to accept it. Additional work normally has time and cost implications, and the team should consider resource effects as well. A request is information to assess; it is not yet a revised agreement. If the change is approved, the baseline is updated accordingly. The baseline therefore supports controlled change. It is neither a reason to ignore valid requests nor a document to rewrite casually whenever someone has a new preference.
- Identify the proposed difference from the agreed scope.
- Review its impact on time, cost, resources and objectives.
- Obtain the approval or rejection decision.
- Update the relevant baselines when an approved change requires it.
Key ideaKeep the agreed reference clear while making approved changes visible.
Key takeaways
- Scope Statement, approved WBS and WBS dictionary make up the scope baseline.
- The dictionary explains work details behind the hierarchy.
- Assess a change against the agreed reference before approving and updating it.