Planning & Controls · 5 November recording reference

Glossary

Short definitions as the module uses them, each linked to the lesson it comes from.

Executable schedule

A delivery model whose activities are defined, connected, resourced, timed and checked against realistic conditions.

Review Lesson 1
Work Breakdown Structure (WBS)

The structure that organizes the full project scope into manageable work.

Review Lesson 1
Work package

The lowest manageable part of the WBS, with a clear deliverable, owner, budget and responsibility.

Review Lesson 1
Activity

A specific measurable action required to complete a work package.

Review Lesson 1
Hard logic

An actual dependency that requires an order of work, such as submitting an exam before it is graded.

Review Lesson 2
Soft logic

A preferred sequence that may be changed if another method of execution is workable.

Review Lesson 2
False logic

A relationship that does not reflect actual delivery, such as linking unrelated activities to manipulate dates.

Review Lesson 2
Finish-to-start (FS)

A relationship in which the predecessor must finish before the successor can start, subject to any stated lag or lead.

Review Lesson 2
Start-to-start (SS)

A relationship constraining the successor's start by the predecessor's start, allowing appropriate overlap.

Review Lesson 2
Finish-to-finish (FF)

A relationship in which the successor cannot finish before the predecessor finishes, subject to any offset.

Review Lesson 2
Start-to-finish (SF)

A relationship in which the predecessor's start controls the successor's finish, illustrated by shift coverage.

Review Lesson 2
Lag

A waiting interval between connected activity events.

Review Lesson 2
Lead

A negative lag that allows a controlled overlap between linked activities.

Review Lesson 2
Hard constraint

An imposed timing requirement such as must finish on that needs a defensible delivery reason.

Review Lesson 2
Productivity

The output achieved by a resource or crew per unit of time; the rate must match the estimate's availability basis.

Review Lesson 3
Critical path

The longest dependent path controlling project duration in the simple unconstrained CPM model used in the session.

Review Lesson 4
Near-critical path

A path with little remaining float that could soon become controlling.

Review Lesson 4
Risk path

A path exposed to disruption that could become controlling even if its current calculation contains substantial float.

Review Lesson 4
Forward pass

Analysis from project start toward finish to calculate early start and early finish dates.

Review Lesson 4
Backward pass

Analysis from the selected finish requirement backward to calculate late finish and late start dates.

Review Lesson 4
Total float

Permitted delay without moving project completion or the relevant required milestone, under the schedule's assumptions.

Review Lesson 5
Free float

Permitted delay without affecting the successor's early start.

Review Lesson 5
Negative float

A calculated indication that the current schedule cannot meet a required date or constraint.

Review Lesson 5
Baseline

The approved schedule used as a reference when comparing actual progress and forecasts.

Review Lesson 6
Gantt chart

A horizontal-bar view of activities against time that helps show duration, overlap and progress.

Review Lesson 6
S-curve

A cumulative measure such as cost, labor hours or quantities plotted over time; its units determine what the curve says.

Review Lesson 6
Fast tracking

Schedule compression by overlapping activities previously planned in sequence, with potential rework and coordination risk.

Review Lesson 7
Crashing

Schedule compression by adding resources or work intensity to feasible controlling work, usually at increased direct cost.

Review Lesson 7