The longest dependent path controls the finish
The recording adds three paths: 3 + 6 + 5 = 14, 3 + 4 + 5 = 12, and 3 + 3 + 5 = 11. It identifies A–D–E as the fourteen-day critical path. The project cannot finish in twelve days simply because another path is shorter; the controlling chain must also be completed. Under the simple unconstrained CPM model presented, critical activities have zero total float. An unrecovered delay on the controlling path delays the project finish. These conclusions depend on the model's relationships, calendars and durations; adding constraints or resource restrictions can require a more careful interpretation.
| Path | Sum | Duration |
|---|---|---|
| A–D–E | 3 + 6 + 5 | 14 days · critical |
| Other path in the comparison | 3 + 4 + 5 | 12 days |
| Other path in the comparison | 3 + 3 + 5 | 11 days |
Read with careOnly the longest path is named in the spoken explanation used here; the other path labels are not reconstructed from an unverified diagram.
Forward asks how early; backward asks how late
The lecturer describes moving from the beginning to the end to calculate early starts and early finishes, then working backward to calculate late finishes and late starts. The passes serve different questions: what can begin as soon as prerequisites allow, and how late can work occur without moving the selected finish requirement? Teaching clarification for a simple finish-to-start network with zero lag: an activity's early finish is its early start plus duration. At a merge, the early start waits for the latest predecessor finish. In the backward pass, late start is late finish minus duration, and a predecessor must respect the earliest permitted successor start. These are explanatory extensions of the source's pass overview; the recording does not work a complete dated network calculation during this recap.
Forward pass
- Move from start toward finish
- Calculate early start and early finish
- Wait for all required predecessors
Backward pass
- Move from finish toward start
- Calculate late finish and late start
- Protect the selected finish requirement
Monitor paths that could become controlling
A near-critical path has little remaining float and can quickly become critical. A risk path is a different concern: its current calculation may contain substantial float, but an uncertain event could create a sufficiently large delay to make it controlling. The session uses adverse weather as a simple illustration. Therefore the project manager watches the current critical path, near-critical paths and exposed risk paths. The label critical identifies the present calculation; it does not eliminate uncertainty elsewhere in the network. Recalculate when durations, progress or dependencies change rather than assuming the first controlling path will remain unchanged.
Key ideaPrioritize the controlling path while watching the small margins and credible disruptions that could change it.
Key takeaways
- The recording's A–D–E path takes fourteen days and is longer than the twelve- and eleven-day alternatives.
- The forward pass calculates early dates; the backward pass calculates late dates.
- Near-critical paths have little margin; risk paths may be exposed despite larger calculated float.
- CPM results depend on the quality and assumptions of the schedule model.