Build honest logic, then use leads, lags and constraints carefully

Every relationship should explain a real handoff or an intentional way of working. Distinguish hard, soft and false logic, understand the four relationship types, and keep meaningful work visible instead of hiding it in lags or imposed dates.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

A relationship needs a reason

Hard logic represents a genuine dependency: in the Q&A, the lecturer cannot grade an examination before students complete and submit it. Soft logic is a preferred sequence that could change: preparing slides before rehearsing is sensible, but rehearsal can begin from a draft. False logic links unrelated work and misrepresents the project. The lecturer contrasts students sitting an exam with the lecturer preparing a separate presentation. Normally every activity, except the project start and finish, needs a predecessor and successor. Otherwise a task may not respond to a delay or appear on the controlling path even when it matters. This is a model-integrity check, not permission to add arbitrary links simply to eliminate an open end.

Three kinds of logic from the recording
KindReason for the linkManagement response
HardThe work truly requires this orderRespect the dependency
SoftThis is a preferred method of workingReview whether another sequence is workable
FalseThe link does not represent deliveryRemove or correct the artificial dependency

Name the two events that are linked

Finish-to-start is the usual relationship: the predecessor must finish before the successor can start. Start-to-start permits overlap once the predecessor starts. Finish-to-finish permits parallel work but constrains completion: the successor cannot finish before the predecessor finishes. Start-to-finish links the predecessor's start to the successor's finish and is uncommon in the examples discussed. The Q&A illustrates start-to-finish with hospital shift coverage. The outgoing night shift cannot finish until the incoming day shift begins. For that relationship, the incoming shift's start is the controlling predecessor event, even though the outgoing shift began earlier in clock time. The lecturer corrects verbal slips between start-to-start and start-to-finish; interpret the event definitions and the coverage example rather than treating every spoken abbreviation as a separate rule.

  • FS Predecessor finish controls successor start.
  • SS Predecessor start controls successor start.
  • FF Predecessor finish controls successor finish.
  • SF Predecessor start controls successor finish; use only with a clear delivery reason.

Read with careThe source recommends clear relationships and treats SF as rare and confusing. Rarity does not make a valid SF relationship inherently wrong or beyond a scheduling tool's capabilities.

Keep meaningful work visible

A lag is a waiting interval between linked activities. A lead is a negative lag that permits controlled overlap. The recording argues that concrete curing should normally be a separate activity because it takes time and needs monitoring; it should not disappear inside an unexplained three-day lag. A hard constraint such as must finish on imposes a date. Constraints need scrutiny because they can obscure what the logic and durations would otherwise predict. Before adding one, identify the real commitment it represents. Before overlapping work, check that the proposed lead is physically possible and that the handoff will produce usable information.

Study-guide applicationIf a review needs an actual draft, describe the draft handoff and review activity. A negative lag alone does not prove that a reviewer will have an adequate draft or that later revisions will be harmless.

Key ideaUse relationships to explain execution; do not manipulate links, lags or fixed dates to make an attractive finish date appear.

Key takeaways

  • Hard logic is required; soft logic is a revisable preference; false logic misrepresents the project.
  • Check the actual start and finish events in every relationship.
  • Give monitorable work its own activity when warranted.
  • A constraint must represent a real commitment rather than conceal an infeasible plan.

Based on Farah Demachkieh's supplied 5 November 2026 class recording. Source notes identify the spoken topics; worked teaching checks, questions and reflections are study-guide additions.