The executable-schedule review

Review the chain from scope to timing, then connect float, baseline control and compression to the management decisions they support.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Build the model before trusting the dates

Define the full scope through the WBS, work packages and measurable activities. Explain dependencies as hard or deliberately chosen soft logic, and remove false links. Use FS, SS, FF or a justified SF relationship according to the events being controlled. Make monitorable work visible rather than hiding it in a lag. Estimate duration through work quantity, productivity and concurrently effective crews, with calendars and interruptions accounted for. Software calculates those inputs; it does not establish whether they represent a workable project.

Read the controlling paths and their margins

The session's paths take fourteen, twelve and eleven days; A–D–E is the fourteen-day controlling path. Forward analysis gives early dates and backward analysis gives late dates. Watch near-critical paths with little margin and risk paths exposed to disruption. Total float protects project completion or the relevant required milestone. Free float protects the successor's early start. Negative float flags an unmet requirement. Explain those meanings before using equations or deciding that an activity can slip.

Preserve the reference and evaluate the intervention

A Gantt chart communicates activity timing. The approved baseline provides a stable comparison for actual progress. An S-curve shows a cumulative measure such as cost, labor hours or quantities; early starts bring work and outflow forward, while late starts defer spending but leave less room to recover. Formal re-baselining belongs to a justified approved change. Fast tracking overlaps work and can introduce rework and coordination risk. Crashing adds resources or intensity and usually adds direct cost. With two twenty-day critical paths, reducing only one to eighteen days leaves the project at twenty. Consider feasible common actions or coordinated combinations, then recalculate the whole network.

Based on Farah Demachkieh's supplied 5 November 2026 class recording. Source notes identify the spoken topics; worked teaching checks, questions and reflections are study-guide additions.