Planning & Controls · 5 November recordingLesson 6

Study explanation · Lesson 06 · 8 min

Use the baseline, Gantt chart and S-curve to explain performance

A Gantt chart makes activity timing visible. The approved baseline supplies the reference for control. Cumulative S-curves connect time with cost, labor or quantities, while early and late plans expose a cash-flow and recovery-margin trade-off.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Choose a view that helps people understand the work

The session presents a Gantt chart as horizontal activity bars against time. It helps many stakeholders see duration, ordering, overlap and progress on one page. The network explains dependencies; the bar view makes their timing easier to discuss. A readable display is useful, but it cannot repair missing scope or incorrect relationships. In the closing Q&A, the lecturer distinguishes large schedules with hundreds of activities, for which Primavera or MS Project can help, from small projects that can use simpler tools such as Excel. This is guidance about proportionate tooling, not a rule that a particular activity count requires one product.

Key ideaChoose software and views that support an understandable model; the team still owns its inputs and interpretation.

Keep the approved comparison point meaningful

Once the relevant authority approves the schedule, it becomes the baseline. Actual progress is compared with that approved plan during execution. Ordinary updates should report performance against the reference rather than silently replacing it with the latest forecast. A major approved change may make the original baseline no longer meaningful and justify formal re-baselining. The lecturer warns against changing the baseline merely to hide poor performance. Keep the difference clear: updating the current schedule records what is happening; approving a replacement baseline changes the authorized comparison point.

Study-guide applicationA deliverable is forecast three days late with unchanged scope. Report the delay and response against the baseline. If the client instead approves a major scope change, assess the new plan through the project's formal change process rather than disguising it as routine progress.

Read what the cumulative curve measures

An S-curve shows cumulative cost, labor hours or quantities over time, depending on its axis. Work commonly begins slowly during planning and mobilization, increases during peak production and levels off toward completion. The planned curve comes from the baseline and supports comparison with actual performance. An early-start plan brings work and cash outflow forward. A late-start plan delays spending and preserves cash longer, but leaves less timing flexibility to recover from a delay. The late-start comparison concerns deferring expenditure, not creating additional schedule protection. The shared slide makes that trade-off explicit even where the spoken explanation is less precise.

Interpret the three S-curve references
CurveWhat it representsDecision implication
Early startWork and outflow occur earlierEarlier production; funding needed earlier
Planned baselineApproved cumulative referenceCompare actual performance on the same measurement basis
Late startWork and spending are deferredCash retained longer; less room to recover

Read with careA cumulative cost line is not automatically a physical-progress line. Check the unit on the vertical axis.

Key takeaways

  • Gantt bars show timing and overlap; relationships still come from the schedule model.
  • Use a stable approved baseline to make performance visible.
  • Formal re-baselining requires a justified approved change.
  • Late starts defer spending but consume timing margin.
  • Read the S-curve's measure before drawing a progress conclusion.

Based on Farah Demachkieh's supplied 5 November 2026 class recording. Source notes identify the spoken topics; worked teaching checks, questions and reflections are study-guide additions.

Your study checkpoint

Ready to continue?

Mark the lesson complete once you have read it and tried its idea on something real.

Next · Lesson 7