Planning & Controls · 5 November recordingLesson 7

Study explanation · Lesson 07 · 9 min

Compress the whole project, including every controlling path

Fast tracking changes overlap. Crashing adds resources or intensity. Both require a management trade-off, and neither helps the finish unless it shortens the controlling work. The live Q&A explains why multiple critical paths can require combinations of crash actions.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Two techniques change different assumptions

Fast tracking overlaps activities previously planned in sequence. It can shorten the schedule without directly adding resources, but increases exposure to rework, coordination problems and quality issues. The overlap must be feasible; a real hard dependency does not disappear because a finish date is urgent. Crashing adds resources or work intensity: extra crews, overtime or additional equipment. It normally increases direct cost and can create communication or productivity problems. The decision should account for cost, quality, coordination and risk, not only the days an optimistic revision appears to save.

Two ways to attempt a shorter duration

Fast tracking

  • Overlap previously sequential activities
  • Does not directly require more resources
  • Check handoffs, rework, coordination and quality

Crashing

  • Add resources or work intensity
  • Usually increases direct cost
  • Check productivity, communication and feasible limits

The controlling paths must all get shorter

The lecturer's Q&A considers two separate critical paths, each twenty days long: A–B–C and D–E–F. Crashing B by two days makes the first path eighteen days, but the second remains twenty. The project therefore remains twenty days. To reach eighteen, both controlling paths must become no longer than eighteen. If an activity is shared by every critical path, shortening it can affect them together. Otherwise the team may need one feasible action on each path at the same time. That is why the learner's earlier worked material began comparing combinations of activities rather than single activities alone.

The live question's two-path example
CasePath A–B–CPath D–E–FProject duration
Initial plan20 days20 days20 days
Crash only B by 2 days18 days20 days20 days
Both paths shortened by 2 days18 days18 days18 days

Read with careThe last case assumes feasible actions on both paths and no other path longer than eighteen days; it is an explicit teaching check on the Q&A's conclusion.

Compare feasible combinations, then recalculate

The discussion prioritizes low-cost opportunities that shorten the critical work and asks learners to look for common activities before moving to combinations. A useful decision compares the cost of an action that affects all controlling paths with the combined cost of actions needed across separate paths. A common activity is a candidate, not automatic proof of the cheapest or physically feasible option. After each compression step, recalculate the full network: another path may become critical, a crash limit may be exhausted, or resource availability may prevent the proposed change. The recording introduces a time-cost trade-off rather than a complete numerical optimization procedure. It closes by distinguishing deterministic scheduling from a probabilistic topic to be developed separately; this session does not supply a worked PERT calculation.

  • Identify every currently controlling path.
  • List feasible shared and separate compression actions.
  • Compare the total cost required for an actual project-duration reduction.
  • Check resources, quality, coordination, rework and risk.
  • Recalculate before committing to the next reduction.

Key ideaA cheaper activity-level reduction is useful only if the combined decision reduces the whole project's duration.

Key takeaways

  • Fast tracking changes overlap; crashing changes resources or work intensity.
  • Shorten controlling work and evaluate the wider delivery consequences.
  • A remaining twenty-day critical path keeps the project at twenty days.
  • Separate controlling paths may require simultaneous crash combinations.
  • Recalculate after each change because the controlling paths can change.

Based on Farah Demachkieh's supplied 5 November 2026 class recording. Source notes identify the spoken topics; worked teaching checks, questions and reflections are study-guide additions.

Your study checkpoint

Ready to continue?

Mark the lesson complete once you have read it and tried its idea on something real.

Next · Summary