Define the work before choosing the team size
The recording introduces duration as the quantity of work divided by productivity per crew multiplied by the number of crews. Written with its grouping explicit, D = Q / (P × N). Q is work quantity, P is output per crew per time unit, and N is the number of crews working concurrently. First identify the resource type: people, equipment, materials or tools. Then define how much work must be done, and decide what resource quantity is required. Choosing headcount before understanding the work can produce an estimate with no defensible connection to the deliverable.
| Input | Meaning | Illustrative unit |
|---|---|---|
| Q | Quantity of work | Units |
| P | Productivity of one crew | Units per crew-day |
| N | Concurrent crews | Crews |
| D | Q divided by P × N | Days |
Read with careUnits and the worked values below are teaching additions used to explain the source's formula.
Check what the arithmetic assumes
Study-guide worked example: 240 units of work, productivity of 20 units per crew-day and two concurrently effective crews give 240 / (20 × 2) = 6 days. The result assumes that the two crews can both produce at that rate, have the necessary equipment and inputs, and can access work at the same time. The arithmetic is an estimate model, not proof that adding crews always cuts duration proportionally. Space, handoffs, coordination and productivity can limit what added resources achieve. The later crashing discussion explicitly returns to productivity and communication problems when work intensity rises.
Study-guide sensitivity checkWith the same 240 units and two crews, output of 15 units per crew-day gives 240 / (15 × 2) = 8 days. Explain why productivity changed rather than replacing the result with the preferred deadline.
An eight-hour day is not eight uninterrupted project hours
The lecturer asks learners to account for meetings, calls and interruptions. A person present for eight hours may have fewer hours available for the scheduled task. The session mentions 75% efficiency in a non-project-oriented organization and 90% in a project-oriented organization as practical estimating rules. Use those as the lecturer's illustrative planning assumptions, not measured facts about every organization. A teaching conversion gives six productive hours at 75%, or 7.2 hours at 90%, from an eight-hour day. The estimate still needs the actual person's workload, calendar and working conditions. Avoid applying the same reduction twice if the productivity rate already reflects those interruptions.
Key ideaExplain whether productivity is based on nominal hours or effective working time, then keep the duration calculation consistent with that basis.
Key takeaways
- Duration relates work quantity to effective output capacity.
- Use consistent units in Q / (P × N).
- Concurrent crews must actually have access, inputs and capacity.
- Availability factors need evidence and should not be counted twice.