Applied case source guide

Applied case: a proposed project charter

This map traces each case part back to the proposed charter, its companion guide, and the Week 3 deck pages it applies. Use it to check which kind of claim you are reading before you rely on it.

How to read the references

“Charter §n” is a section of the proposed charter, “Guide §n” a section of its companion guide, and “Deck pp.” the PDF page numbers of the Week 3 deck. Four kinds of claim are kept apart: course concepts cite the deck, case facts cite the charter, applied reasoning cites the guide, and applied choices, the numbers and rules the author designed for this case, carry their own Applied choice callout.

The case documents

One charter, one companion guide

The charter is a project charter for “2,000 Books for Learning”, a book donation and distribution initiative, at version 1.0 and proposed for sponsor approval as an academic scenario. It has nine numbered sections and a closing basis line. The companion guide explains why each charter choice was made, in eleven numbered sections with a note on sources and provenance. Neither document is republished here.

Charter and companion guide by Fadi Nicolas Zahhar, 18 September 2026

Case map · Charter, Guide and Deck
Case partCharterGuideDeck lessons appliedDeck pages
1 · The brief and the Week 2 baselineTitle block, §1§1-21 What a charter is; 2 Componentspp. 2-13
2 · Purpose, scope, and the charter and plan line§1-2§3; §4 on scope2 Components; 3 Why and whopp. 9-29
3 · Six SMART objectives and their evidence§3§42 Componentspp. 9-12, 19-20
4 · Budget, milestones and assumptions§4-5§52 Componentspp. 9-12, 23-24
5 · Authority within limits§6§6; §8 on RACI7 Delegation; 8 Authority and RACIpp. 58-73
6 · The top three risks§7§74 Risk; 5 Assessing riskspp. 30-45
7 · Stakeholders and sign-off§8-9§8; §9 principles only; §106 Stakeholders; 3 Why and whopp. 27-29, 46-57

Part 01

The brief and the Week 2 baseline

The charter is written to answer one question for the sponsor, and it builds on the Week 2 definition of the same book project rather than replacing it.

Open the case part
The case and its status

The title block and Section 1 give the headline figures, the place, the delivery model and the six-week clock. Section 9 explains why the signature lines are blank.

Charter title block, §1, §9
The central question

The guide opens with the question a sponsor must be able to answer and maps each brief requirement to a charter section.

Guide §1
Deck components

The deck's two component tables list assumptions and constraints, timeline and budget, and approval. The cross-walk to charter sections is a study aid built for this module.

Deck pp. 9-13 · Guide §1
The Week 2 baseline

The guide explains why the Week 2 project was kept, how each baseline item is developed, and what was not assumed.

Guide §2 · Charter §1-3

Part 02

Purpose, scope, and where the charter ends and the plan begins

The charter separates the need, the deliverable, the outcome and a benefit it will not promise, draws a firm scope boundary, and leaves route-level detail to the plan.

Open the case part
Need, outcome and benefit

The charter states the assumed need and declines to claim a literacy improvement; the guide explains the four-way distinction.

Charter §1 · Guide §3 · Deck pp. 5-12, 19-24
Included work, deliverables and exclusions

Section 2 lists the included work, seven deliverables, nine exclusions and the rule for any expansion.

Charter §2
Why exclusions matter

The guide explains that exclusions are scope decisions that protect the six-week commitment.

Guide §4 · Charter §2
Charter versus plan

The guide's table sorts case details into charter and plan, following the deck's comparison, and adds the truck-route test.

Guide §3 · Deck pp. 14-17, 27-29
Stable versus evolving

The guide explains the choice of a stable, milestone-based charter and how routine and charter-level changes are handled.

Guide §3 · Charter §6 · Deck pp. 2-4, 25-26

Part 03

Six SMART objectives and their evidence

Six proposed objectives turn the scope into outcomes a sponsor can verify, each with a deadline, a target, and the record that will prove it.

Open the case part
Scope versus objectives

The guide contrasts an activity with an outcome that carries its own evidence.

Guide §4
The six objectives

Section 3 sets out each objective's deadline, target and verification, and says the targets are proposed, not achieved.

Charter §3 · Deck pp. 9-12
SMART and achievability

The guide applies each SMART element to O1 and explains why achievable is not a guarantee.

Guide §4 · Deck pp. 19-20
Evidence and the carton formula

The guide explains the choice of verifiable evidence and identifies the carton denominator as its own refinement.

Charter §3 · Guide §4

Part 04

Budget, milestones and assumptions

A transparent cost build-up with contingency inside the ceiling, six milestones counted from the day of signature, and the assumptions that could still undo them.

Open the case part
Cost build-up and contingency

Section 5 sets out the four allowances, the base, the 15% contingency and the rules for using it; the guide explains the arithmetic.

Charter §5 · Guide §5
In-kind contributions

Section 4 states the in-kind assumption, and the guide explains why it is disclosed and when the estimate must be revisited.

Charter §4 · Guide §5
Milestones and the six-week clock

Section 5 lists the milestones and counts the six weeks from authorization; the guide explains why the duration is plausible only under conditions.

Charter §5 · Guide §5
Assumptions and constraints

Section 4 lists the fixed constraints and preconditions; the guide gives an example of each of the four terms.

Charter §4 · Guide §5 · Deck pp. 9-12, 23-24

Part 05

Authority within limits

The sponsor keeps the fundamental commitments. The Project Manager decides within five proportionate limits, escalates fast, and logs every use of authority so small steps cannot add up unseen.

Open the case part
Who owns what

Section 6 sets out what the sponsor keeps and what the Project Manager does; the guide separates responsibility from authority.

Charter §6 · Guide §6 · Deck pp. 59-63, 69-72
Delegated limits and their reasons

Section 6 gives the five decision areas and their limits, and the guide explains why each limit was chosen.

Charter §6 · Guide §6
The deck's example versus the charter

The comparison sets the deck's illustrative table beside the charter's limits; the guide explains why the example values were not copied.

Deck p. 64 · Charter §6 · Guide §6
Reporting, escalation and logging

Section 6 sets weekly reporting, the escalation windows, the rule that silence is not approval, and the decision log.

Charter §6
Decision tests, RACI and the principle

The guide works through three decisions, explains why RACI does not replace the authority table, and states the competence and authority principle.

Guide §6, §8, §9 · Deck pp. 59-73

Part 06

The top three risks

Three medium-likelihood, high-impact risks, each found by testing an assumption behind an objective, each with a monitor, a first response and a trigger for escalation.

Open the case part
Framing and ratings

Section 7 explains why these risks come first and that the ratings are qualitative; the guide explains how the charter follows the deck's notes.

Charter §7 · Guide §7 · Deck pp. 31-45
R1, R2 and R3

Each risk carries a class, a rating, an if-then statement, a monitor, an initial response and an escalation condition.

Charter §7
Assumptions tested

The guide pairs each risk with the assumption it tests and the objective it threatens.

Guide §7 · Deck pp. 37-38
Classification and exclusions

The guide explains the internal and external classes and why customs delays were not copied.

Guide §7 · Deck pp. 33-34
Validation methods

The guide lists how the risks would be validated in practice and why Delphi is not added.

Guide §7 · Deck pp. 37-41

Part 07

Stakeholders and sign-off

A provisional, role-based stakeholder list placed on the deck's grid, then the acceptance evidence and the three separate decisions that authorize, receive and close the project.

Open the case part
The stakeholder list

Section 8 gives eight role-based stakeholders with importance, power and interest, and engagement notes, and says the list is provisional.

Charter §8 · Deck pp. 47-52
Grid placement

The figure places the charter's ratings on the deck's grid; the midline placements are this module's reading of three-level ratings on a two-by-two grid.

Charter §8 · Deck p. 53
Legitimacy and salience

The guide explains why beneficiaries without budget authority still matter, using the salience model's insight.

Guide §8 · Deck pp. 53-57
Acceptance and authorization

Section 9 sets the acceptance evidence and what the signature does and does not do; the guide separates the three decisions.

Charter §9 · Guide §8
Prospective wording and principles

The guide explains the prospective wording and summarizes the case; its transferable principles are used without any client application.

Guide §8, §9, §10

Source appendix

Where the case needs a careful reading

Read with care

Baseline provenance

The Week 2 baseline was recovered from a drafting conversation. It was not checked against the submitted Week 2 document (Guide §2 and its source note).

An academic scenario

The location, the NGO, the schools, the suppliers, the prices and the sponsor are planning assumptions. No field work, market research or supplier interview was done (Charter §1, Guide §2 and its sources).

Applied thresholds

The USD 1,000, 400, 300 and 600 limits, the three-day resequencing allowance and the escalation windows are the author's design choices, not course or industry numbers. The deck's page 64 figures are illustrations (Guide §6).

Qualitative ratings

The deck's page 35 slide says “Quantitative Impact Summary”, but its notes on page 36 and pages 42-43 describe a high, medium or low assessment. The charter follows the notes (Guide §7).

Stable or evolving

The deck calls the charter both broad and stable and a living point of reference. The charter handles this through delegated limits for routine change and sponsor reauthorization for charter-level change (Guide §3).

Three-level ratings on a two-by-two grid

The charter rates some stakeholders medium or potentially high, while the deck's page 53 grid has only low and high. The figure places those roles on the midlines instead of choosing a quadrant. This is an observation made for this module, not a point from the guide.

Achievable is conditional

The SMART achievable element rests on assumptions still to be validated; it is a defensible basis, not a guarantee (Guide §4).

R3's classification

Calling R3 internal classifies the team's own validation process. It does not claim that school behaviour is controllable (Guide §7).

Checked against the charter, the guide and the deck pages cited in each note.

Deliberately left out

These parts of the source documents are not part of the study case:

  • The names of client projects from the author's professional work, and the guide's column applying the principles to them. Only the guide's generic principles are used.
  • Submission logistics, such as deadlines, word counts, upload locations and instructions about what to submit.
  • The guide's direct address to its author and its personal-guide label, replaced by a neutral learner voice and the single credit on this page.
  • A callout about the author's earlier feedback. Only its principle is kept: targets are not achievements.
  • The signature lines, which are described in the text rather than reproduced.

A prospective voice

The charter is a proposal that has not been authorized. The case therefore says “will”, “proposed” and “requires”, and never describes a target as delivered or achieved. A real sponsor would need named partners, validated quotations and confirmed capacity before the proposal could become an operational commitment.

The deck lessons and their slide-level sources are in the Module 3 source guide.