Project Management · Module 6 · Applied case reference
Applied glossary
Terms as this calculation uses them. Where a term is the author's own choice rather than course vocabulary, the source line says so.
- Activity table
Brief
The brief’s list of seven activities, A to G, with their predecessors and durations in days.
Review Part 1- Critical
Guide §1
In this case, an activity whose delay delays the project finish. It says nothing about importance or difficulty.
Review Part 1- Stated assumption
Submission p. 1 · applied choice
A modelling choice the answer declares because the brief is silent: finish-to-start links, no leads or lags, fixed durations, resources for the overlap, day 0.
Review Part 1- Split after C
Guide §3 · Deck p. 51
The point where the network diverges into prototype development (D) and testing (E), which both follow design.
Review Part 2- Merge at F
Guide §3 · Deck p. 51
The point where both branches converge: final implementation needs D and E finished.
Review Part 2- Complete dependency path
Submission p. 1
A route through the network from initiation to closure. This network has two, of 22 and 21 days, and they run concurrently.
Review Part 2- Forward pass
Submission p. 2 · Deck p. 81
The sweep from start to end that gives each activity’s early start and early finish.
Review Part 3- Day 0
Guide §5 · applied choice
The starting boundary of the schedule, not an extra working day.
Review Part 3- Schedule days
Submission p. 1 · Guide §5
Relative days counted from day 0, used because the brief gives no start date or working calendar.
Review Part 3- Backward pass
Submission p. 2 · Deck p. 83
The sweep from the project finish back to the start that gives each activity’s late finish and late start.
Review Part 4- Zero-float chain
Submission p. 2
The activities with no total float, A, B, C, D, F and G, which confirm the critical path.
Review Part 4- Shared allowance
Guide §7
The guide’s description of float that can be used only once, by a late start or a longer duration, not both.
Review Part 4- What-if calculation
Guide §8
A derived result from changing one duration, with everything else as in the brief. Not part of the submitted answer.
Review Part 5- Readiness at a merge
Guide §8
Which unfinished dependency controls when the next activity can start.
Review Part 5- Answer box
Submission p. 1
The two results stated at the top of the submission, before any working.
Review Part 6