Project Management · Module 6 · Applied case reference

Applied glossary

Terms as this calculation uses them. Where a term is the author's own choice rather than course vocabulary, the source line says so.

Activity table

Brief

The brief’s list of seven activities, A to G, with their predecessors and durations in days.

Review Part 1
Critical

Guide §1

In this case, an activity whose delay delays the project finish. It says nothing about importance or difficulty.

Review Part 1
Stated assumption

Submission p. 1 · applied choice

A modelling choice the answer declares because the brief is silent: finish-to-start links, no leads or lags, fixed durations, resources for the overlap, day 0.

Review Part 1
Split after C

Guide §3 · Deck p. 51

The point where the network diverges into prototype development (D) and testing (E), which both follow design.

Review Part 2
Merge at F

Guide §3 · Deck p. 51

The point where both branches converge: final implementation needs D and E finished.

Review Part 2
Complete dependency path

Submission p. 1

A route through the network from initiation to closure. This network has two, of 22 and 21 days, and they run concurrently.

Review Part 2
Forward pass

Submission p. 2 · Deck p. 81

The sweep from start to end that gives each activity’s early start and early finish.

Review Part 3
Day 0

Guide §5 · applied choice

The starting boundary of the schedule, not an extra working day.

Review Part 3
Schedule days

Submission p. 1 · Guide §5

Relative days counted from day 0, used because the brief gives no start date or working calendar.

Review Part 3
Backward pass

Submission p. 2 · Deck p. 83

The sweep from the project finish back to the start that gives each activity’s late finish and late start.

Review Part 4
Zero-float chain

Submission p. 2

The activities with no total float, A, B, C, D, F and G, which confirm the critical path.

Review Part 4
Shared allowance

Guide §7

The guide’s description of float that can be used only once, by a late start or a longer duration, not both.

Review Part 4
What-if calculation

Guide §8

A derived result from changing one duration, with everything else as in the brief. Not part of the submitted answer.

Review Part 5
Readiness at a merge

Guide §8

Which unfinished dependency controls when the next activity can start.

Review Part 5
Answer box

Submission p. 1

The two results stated at the top of the submission, before any working.

Review Part 6