Two rules
Early start is the first time an activity can begin after all its predecessors finish. Early finish adds the activity’s duration to that start. These are the forward-pass rules of the Week 6 worked example.
- Early start = the largest early finish among the immediate predecessors. With no predecessor, early start is 0.
- Early finish = early start + duration.
Activity by activity
Applied to the brief’s table, the rules give every early date in one sweep from A to G.
| Activity | Why this is its early start | ES | EF |
|---|---|---|---|
| A | No predecessor: start at 0 | 0 | 0 + 2 = 2 |
| B | A finishes at 2 | 2 | 2 + 4 = 6 |
| C | B finishes at 6 | 6 | 6 + 3 = 9 |
| D | C finishes at 9 | 9 | 9 + 5 = 14 |
| E | C finishes at 9 | 9 | 9 + 4 = 13 |
| F | Both D and E must finish: max(14, 13) | 14 | 14 + 6 = 20 |
| G | F finishes at 20 | 20 | 20 + 2 = 22 |
Why the maximum at F
E is ready at day 13, but D is not ready until day 14. Starting F at day 13 would break D’s dependency, so F takes the later finish, 14, because it must wait for every predecessor.
Key ideaThe predecessor finish times are not added. They are positions on the same schedule, not separate durations.
Why not 26 days?
Adding all seven durations gives 26 days, but that treats D and E as if one followed the other, counting their section as 5 + 4 = 9 days. In fact both fit inside one five-day window.
The calculationProject duration = 2 + 4 + 3 + max(5, 4) + 6 + 2 = 22 days.
Read with careBy coincidence, 26 days is also the duration of the deck’s own worked example in Lesson 6. The two have nothing to do with each other.
Day 0 is a boundary
Day 0 is the starting boundary, not an extra working day. Activity A runs from time 0 to time 2, which is two days. Shown with day 1 as the first day instead, A occupies days 1 and 2 and B begins on day 3; the durations do not change. Keep one convention throughout. Week 6 also starts its forward pass at day 0.
Applied choiceThe submission states the day-0 convention as an assumption on its first page.
Schedule days, not a date
No project start date, weekend pattern or holiday calendar is provided. The answer is therefore 22 schedule days, not a calendar completion date.
Key ideaThe guide adds a reminder that is easy to blur: the date an assignment is due is not the date the project in it finishes.
Key takeaways
- ES = the largest predecessor EF; EF = ES + duration; the first activity starts at 0.
- At a merge, wait for the latest predecessor; never add predecessor finishes.
- The forward pass ends at day 22; adding every duration gives 26 because it puts D and E in sequence.
- Day 0 is a boundary, and the result is 22 schedule days, not a calendar date.