Project Management · Module 6Applied casePart 3

Applied case · Part 03 · 14 min

The forward pass: 22 days, not 26

Moving from the start of the network to the end gives each activity’s early start and early finish. The only judgment call is at F, which must wait for the later of D and E. The pass ends at day 22, and it shows why simply adding every duration, 26 days, is wrong.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Two rules

Early start is the first time an activity can begin after all its predecessors finish. Early finish adds the activity’s duration to that start. These are the forward-pass rules of the Week 6 worked example.

  1. Early start = the largest early finish among the immediate predecessors. With no predecessor, early start is 0.
  2. Early finish = early start + duration.

Activity by activity

Applied to the brief’s table, the rules give every early date in one sweep from A to G.

The forward pass · Guide §4 · Submission p. 2
ActivityWhy this is its early startESEF
ANo predecessor: start at 000 + 2 = 2
BA finishes at 222 + 4 = 6
CB finishes at 666 + 3 = 9
DC finishes at 999 + 5 = 14
EC finishes at 999 + 4 = 13
FBoth D and E must finish: max(14, 13)1414 + 6 = 20
GF finishes at 202020 + 2 = 22

Why the maximum at F

E is ready at day 13, but D is not ready until day 14. Starting F at day 13 would break D’s dependency, so F takes the later finish, 14, because it must wait for every predecessor.

Key ideaThe predecessor finish times are not added. They are positions on the same schedule, not separate durations.

Why not 26 days?

Adding all seven durations gives 26 days, but that treats D and E as if one followed the other, counting their section as 5 + 4 = 9 days. In fact both fit inside one five-day window.

The calculationProject duration = 2 + 4 + 3 + max(5, 4) + 6 + 2 = 22 days.

Read with careBy coincidence, 26 days is also the duration of the deck’s own worked example in Lesson 6. The two have nothing to do with each other.

Day 0 is a boundary

Day 0 is the starting boundary, not an extra working day. Activity A runs from time 0 to time 2, which is two days. Shown with day 1 as the first day instead, A occupies days 1 and 2 and B begins on day 3; the durations do not change. Keep one convention throughout. Week 6 also starts its forward pass at day 0.

Applied choiceThe submission states the day-0 convention as an assumption on its first page.

Schedule days, not a date

No project start date, weekend pattern or holiday calendar is provided. The answer is therefore 22 schedule days, not a calendar completion date.

Key ideaThe guide adds a reminder that is easy to blur: the date an assignment is due is not the date the project in it finishes.

Key takeaways

  • ES = the largest predecessor EF; EF = ES + duration; the first activity starts at 0.
  • At a merge, wait for the latest predecessor; never add predecessor finishes.
  • The forward pass ends at day 22; adding every duration gives 26 because it puts D and E in sequence.
  • Day 0 is a boundary, and the result is 22 schedule days, not a calendar date.

Study explanation of an academic critical path submission and its study guide, read against the supplied Week 6: Scheduling course deck. Open the source notes above to see which document each claim comes from.