Case context reference
Critical path analysis: the full reference
Everything this case is built from, in one place: the brief’s activity table, every calculation recomputed, the what-if study, the deck check and the points that need a careful reading.
Three documents, kept apart throughout. The assignment brief supplies the task and the activity table. A two-page submission answers it. The author’s four-page study guide explains the submission and is not part of the assessed work. All three are compared against the Week 6 deck, cited by PDF page. The author’s name, the due date and the upload steps are left out, and neither document is republished.
The brief gives activities, predecessors and durations only. Finish-to-start links, no leads or lags, fixed durations, enough resources for D and E to overlap, day 0 and relative schedule days are the author’s stated assumptions. Every number below was recomputed from the brief’s table, and all of them match both documents. Open the case source guide
| Activity | Predecessor(s) | Duration (days) |
|---|---|---|
| A · Project initiation | None | 2 |
| B · Requirement analysis | A | 4 |
| C · Design | B | 3 |
| D · Prototype development | C | 5 |
| E · Testing | C | 4 |
| F · Final implementation | D and E | 6 |
| G · Project closure | F | 2 |
| Path or check | Calculation | Result |
|---|---|---|
| A → B → C → D → F → G | 2 + 4 + 3 + 5 + 6 + 2 | 22 days · critical |
| A → B → C → E → F → G | 2 + 4 + 3 + 4 + 6 + 2 | 21 days |
| Project duration | 2 + 4 + 3 + max(5, 4) + 6 + 2 | 22 schedule days |
| Sum of all durations | 2 + 4 + 3 + 5 + 4 + 6 + 2 | 26 days · wrong, because it puts D and E in sequence |
| Activity | Duration | ES | EF | LS | LF | Total float | Free float | Critical? |
|---|---|---|---|---|---|---|---|---|
| A | 2 | 0 | 2 | 0 | 2 | 0 | 0 | Yes |
| B | 4 | 2 | 6 | 2 | 6 | 0 | 0 | Yes |
| C | 3 | 6 | 9 | 6 | 9 | 0 | 0 | Yes |
| D | 5 | 9 | 14 | 9 | 14 | 0 | 0 | Yes |
| E | 4 | 9 | 13 | 10 | 14 | 1 | 1 | No |
| F | 6 | 14 | 20 | 14 | 20 | 0 | 0 | Yes |
| G | 2 | 20 | 22 | 20 | 22 | 0 | 0 | Yes |
Read with careThe submission reports total float; the guide adds E’s free float, 14 − 13 = 1. The other free float values apply the same deck formula and are this reference’s own calculation. Project float cannot be calculated, because the brief imposes no completion date.
| One change from the brief | Duration | What it shows |
|---|---|---|
| E takes 5 days | 22 days | Both paths equally long and critical |
| E takes 6 days | 23 days | The route through E becomes critical |
| D takes 4 days | 21 days | Both branches take 4 days; both paths critical |
| D takes 3 days | 21 days | E now governs; shortening D further saves nothing |
| E takes 3 days | 22 days | Finishing the non-critical branch earlier does not shorten the project |
Read with careDerived calculations from the study guide, not part of the submitted answer.
| Case part | Main sources |
|---|---|
| 1 · The brief | Brief · Guide §1-2, §9 · Submission p. 1 |
| 2 · Reading the network | Submission p. 1 · Guide §3, §5 · Deck pp. 33, 38, 49, 51 |
| 3 · The forward pass | Submission p. 2 · Guide §4-5 · Deck pp. 72, 81 |
| 4 · Backward pass and float | Submission p. 2 · Guide §6-7 · Deck pp. 74, 76, 79, 83 |
| 5 · What would change it | Guide §8 · Deck p. 76 |
| 6 · The two-page submission | Submission pp. 1-2 · Guide §9-10 |
| Claim in the submission or guide | Deck | Result |
|---|---|---|
| Activity-on-node networks | p. 33 | Matches |
| Finish-to-start links as the assumed relationship | p. 38 | Matches: the deck calls finish to start the most common type; the choice to use it throughout is the author’s |
| No leads or lags | p. 49 | Consistent with the deck’s definitions; the choice is the author’s |
| C diverges into D and E; F converges | p. 51 | Matches |
| CPM finds the longest path, which governs duration | p. 72 | Matches |
| Total float and project float definitions | p. 74 | Matches |
| Near-critical activities need attention | p. 76 | Matches |
| TF = LS − ES = LF − EF; free float = next ES − EF | p. 79 | Matches |
| Forward-pass rules, starting at day 0 | p. 81 | Matches |
| Backward-pass rules | p. 83 | Matches |
| The deck’s prose says 26 minus 7 is 7; the diagram shows 19 | p. 83 | Matches the Week 6 module’s own finding |
Read with careNo contradiction with the deck was found. Every number in the case was also recomputed from the brief’s table, and all match both documents.
Reference appendix
What the guide adds, and what to read with care
Read with care
The brief gives only activities, predecessors and durations. Finish-to-start links, no leads or lags, fixed durations, enough resources for D and E to overlap, day 0 and relative schedule days are the author’s stated assumptions.
On many real projects testing would follow prototype development. The brief makes testing depend only on design, and the answer keeps the table as given; the guide says a real team would validate that link.
The brief asks for the critical path and the duration. The backward pass, float, free float and the what-if table are added analysis; the what-if rows are not part of the submission at all.
No start date or working calendar is supplied, so day 22 is a schedule day, not a calendar date. The submission deadline is not the project’s finish date.
Adding all seven durations gives 26 days, which is also the duration of the deck’s own worked example. The two numbers are unrelated. This is the case’s observation, not the documents’.
Part 5 links the what-if results to Week 6’s compression methods for study. The submission and guide deliberately leave compression out.
The assignment brief was supplied with the documents and is reproduced here only for its task and activity table. Its dates and upload steps are left out.
Checked against the brief, the submission, the study guide and the Week 6 deck.
Key points from the study guide
- “Critical” describes the effect on the finish date, not importance or difficulty; F is the longest single activity, but the answer is a complete path (Guide §1).
- The activities and durations are given, so no new breakdown or estimates are needed; path totals answer, and the two passes verify and explain (Guide §2).
- C diverges into D and E and F converges; the brief does not put D before E, so inserting that link would change the problem (Guide §3).
- The 21-day route does not mean a 21-day project: both branches are required work (Guide §5).
- Day 0 is a boundary, not a working day; with no start date or calendar the answer is 22 schedule days, and the submission deadline is not the project’s finish (Guide §5).
- E’s one day of float is a shared allowance: a late start and a longer duration together push the project to day 23 (Guide §7).
- At a merge point, ask which unfinished dependency controls readiness for the next activity (Guide §8).
- The backward pass goes beyond the brief; compression, resource limits and contingency are left out because they would change the scenario (Guide §9).