Case context reference

Critical path analysis: the full reference

Everything this case is built from, in one place: the brief’s activity table, every calculation recomputed, the what-if study, the deck check and the points that need a careful reading.

The sources

Three documents, kept apart throughout. The assignment brief supplies the task and the activity table. A two-page submission answers it. The author’s four-page study guide explains the submission and is not part of the assessed work. All three are compared against the Week 6 deck, cited by PDF page. The author’s name, the due date and the upload steps are left out, and neither document is republished.

How to use this reference

The brief gives activities, predecessors and durations only. Finish-to-start links, no leads or lags, fixed durations, enough resources for D and E to overlap, day 0 and relative schedule days are the author’s stated assumptions. Every number below was recomputed from the brief’s table, and all of them match both documents. Open the case source guide

The activity table supplied with the assignment · Brief
ActivityPredecessor(s)Duration (days)
A · Project initiationNone2
B · Requirement analysisA4
C · DesignB3
D · Prototype developmentC5
E · TestingC4
F · Final implementationD and E6
G · Project closureF2
The answer · Submission pp. 1-2
Path or checkCalculationResult
A → B → C → D → F → G2 + 4 + 3 + 5 + 6 + 222 days · critical
A → B → C → E → F → G2 + 4 + 3 + 4 + 6 + 221 days
Project duration2 + 4 + 3 + max(5, 4) + 6 + 222 schedule days
Sum of all durations2 + 4 + 3 + 5 + 4 + 6 + 226 days · wrong, because it puts D and E in sequence
Every schedule value, recomputed from the brief · Submission p. 2 · Guide §4-7
ActivityDurationESEFLSLFTotal floatFree floatCritical?
A2020200Yes
B4262600Yes
C3696900Yes
D591491400Yes
E4913101411No
F61420142000Yes
G22022202200Yes

Read with careThe submission reports total float; the guide adds E’s free float, 14 − 13 = 1. The other free float values apply the same deck formula and are this reference’s own calculation. Project float cannot be calculated, because the brief imposes no completion date.

What would change completion · Guide §8, each row recomputed
One change from the briefDurationWhat it shows
E takes 5 days22 daysBoth paths equally long and critical
E takes 6 days23 daysThe route through E becomes critical
D takes 4 days21 daysBoth branches take 4 days; both paths critical
D takes 3 days21 daysE now governs; shortening D further saves nothing
E takes 3 days22 daysFinishing the non-critical branch earlier does not shorten the project

Read with careDerived calculations from the study guide, not part of the submitted answer.

Part map · where each source is used
Case partMain sources
1 · The briefBrief · Guide §1-2, §9 · Submission p. 1
2 · Reading the networkSubmission p. 1 · Guide §3, §5 · Deck pp. 33, 38, 49, 51
3 · The forward passSubmission p. 2 · Guide §4-5 · Deck pp. 72, 81
4 · Backward pass and floatSubmission p. 2 · Guide §6-7 · Deck pp. 74, 76, 79, 83
5 · What would change itGuide §8 · Deck p. 76
6 · The two-page submissionSubmission pp. 1-2 · Guide §9-10
Week 6 references checked against the deck
Claim in the submission or guideDeckResult
Activity-on-node networksp. 33Matches
Finish-to-start links as the assumed relationshipp. 38Matches: the deck calls finish to start the most common type; the choice to use it throughout is the author’s
No leads or lagsp. 49Consistent with the deck’s definitions; the choice is the author’s
C diverges into D and E; F convergesp. 51Matches
CPM finds the longest path, which governs durationp. 72Matches
Total float and project float definitionsp. 74Matches
Near-critical activities need attentionp. 76Matches
TF = LS − ES = LF − EF; free float = next ES − EFp. 79Matches
Forward-pass rules, starting at day 0p. 81Matches
Backward-pass rulesp. 83Matches
The deck’s prose says 26 minus 7 is 7; the diagram shows 19p. 83Matches the Week 6 module’s own finding

Read with careNo contradiction with the deck was found. Every number in the case was also recomputed from the brief’s table, and all match both documents.

Reference appendix

What the guide adds, and what to read with care

Read with care

Assumptions, not facts

The brief gives only activities, predecessors and durations. Finish-to-start links, no leads or lags, fixed durations, enough resources for D and E to overlap, day 0 and relative schedule days are the author’s stated assumptions.

Testing beside prototyping

On many real projects testing would follow prototype development. The brief makes testing depend only on design, and the answer keeps the table as given; the guide says a real team would validate that link.

More than the brief asks

The brief asks for the critical path and the duration. The backward pass, float, free float and the what-if table are added analysis; the what-if rows are not part of the submission at all.

Schedule days, not dates

No start date or working calendar is supplied, so day 22 is a schedule day, not a calendar date. The submission deadline is not the project’s finish date.

A coincidence of 26

Adding all seven durations gives 26 days, which is also the duration of the deck’s own worked example. The two numbers are unrelated. This is the case’s observation, not the documents’.

Compression is study context

Part 5 links the what-if results to Week 6’s compression methods for study. The submission and guide deliberately leave compression out.

The brief is in the session, not the library

The assignment brief was supplied with the documents and is reproduced here only for its task and activity table. Its dates and upload steps are left out.

Checked against the brief, the submission, the study guide and the Week 6 deck.

Key points from the study guide

  • “Critical” describes the effect on the finish date, not importance or difficulty; F is the longest single activity, but the answer is a complete path (Guide §1).
  • The activities and durations are given, so no new breakdown or estimates are needed; path totals answer, and the two passes verify and explain (Guide §2).
  • C diverges into D and E and F converges; the brief does not put D before E, so inserting that link would change the problem (Guide §3).
  • The 21-day route does not mean a 21-day project: both branches are required work (Guide §5).
  • Day 0 is a boundary, not a working day; with no start date or calendar the answer is 22 schedule days, and the submission deadline is not the project’s finish (Guide §5).
  • E’s one day of float is a shared allowance: a late start and a longer duration together push the project to day 23 (Guide §7).
  • At a merge point, ask which unfinished dependency controls readiness for the next activity (Guide §8).
  • The backward pass goes beyond the brief; compression, resource limits and contingency are left out because they would change the scenario (Guide §9).

Study the parts