Case source guide

Applied case: critical path analysis

Where each part of this case comes from, and how its Week 6 page references stand against the course deck.

The three sources

The case reads the assignment brief, which supplies the activity table; a two-page submission that answers it; and the author's personal study guide, which explains the submission and is not part of the assessed work. Page and section numbers refer to those documents. Neither document is republished here.

Why there is a deck check

Both documents cite the Week 6 deck by PDF page. That deck is in this library, so every reference was checked against the actual pages and the result is published below. The check is this case's own work. Open the full case reference

Case map · Brief, Submission, Guide and Deck
Case partSubmissionGuideCourse lessons applied
1 · The briefp. 1: answer box, method and assumptions, inputs§1-2, §9Week 6: the critical path method, sequencing
2 · Reading the networkp. 1: network and path comparison§3, §5Week 6: sequencing, dependencies
3 · The forward passp. 2: rules, table, convergence at F§4-5Week 6: the critical path method, preparing the schedule
4 · Backward pass and floatp. 2: rules, table, backward check, testing flexibility§6-7Week 6: the critical path method
5 · What would change itNot in the submission§8Week 6: the critical path method, schedule compression
6 · The two-page submissionpp. 1-2§9-10Week 6: the critical path method, summary

Read with careThe guide numbers its sections 1 to 10 and ends with an unnumbered reference reading map.

Week 6 references checked against the deck
Claim in the submission or guideDeckResult
Activity-on-node networksp. 33Matches
Finish-to-start links as the assumed relationshipp. 38Matches: the deck calls finish to start the most common type; the choice to use it throughout is the author’s
No leads or lagsp. 49Consistent with the deck’s definitions; the choice is the author’s
C diverges into D and E; F convergesp. 51Matches
CPM finds the longest path, which governs durationp. 72Matches
Total float and project float definitionsp. 74Matches
Near-critical activities need attentionp. 76Matches
TF = LS − ES = LF − EF; free float = next ES − EFp. 79Matches
Forward-pass rules, starting at day 0p. 81Matches
Backward-pass rulesp. 83Matches
The deck’s prose says 26 minus 7 is 7; the diagram shows 19p. 83Matches the Week 6 module’s own finding

Read with careNo contradiction with the deck was found. Every number in the case was also recomputed from the brief’s table, and all match both documents.

Part 01

The brief, and what it really tests

The assignment gives seven activities with their predecessors and durations, and asks for two results: the critical path and the total project duration. Underneath, it tests whether you can tell activities that must follow one another from activities that can run side by side.

Open the case part
The task and the table

Two results from seven activities, in a two-page document.

Brief
What the assignment tests

Sequential against concurrent activities; critical means effect on the finish.

Guide §1 · Deck p. 72
Why this approach

Path totals, then both passes, using Week 6 methods.

Guide §2 · Deck pp. 33, 72, 79, 81, 83
Assumptions

Finish to start, no leads or lags, fixed durations, resources for the overlap, day 0.

Submission p. 1 · Guide §3

Part 02

C splits, F joins: reading the network

The decisive detail is in the predecessor column. C is the only predecessor of both D and E, so the network splits after design; F needs both, so it joins again before implementation. That gives two complete paths, of 22 and 21 days.

Open the case part
C splits; F joins

Divergence and convergence in the assignment network.

Guide §3 · Deck p. 51
No D-to-E link

The supplied table is preserved; validate such links in real delivery.

Guide §3
Network and path comparison

The two complete paths and why the route through D governs.

Submission p. 1 · Guide §5
Assumptions behind the links

Finish to start, no leads or lags, resources for the overlap.

Submission p. 1 · Guide §3 · Deck pp. 38, 49

Part 03

The forward pass: 22 days, not 26

Moving from the start of the network to the end gives each activity’s early start and early finish. The only judgment call is at F, which must wait for the later of D and E. The pass ends at day 22, and it shows why simply adding every duration, 26 days, is wrong.

Open the case part
Forward-pass rules

The maximum predecessor finish, plus duration.

Guide §4 · Submission p. 2 · Deck p. 81
The early dates

A 0-2 through G 20-22.

Guide §4 · Submission p. 2
Convergence at F

ES(F) = max(14, 13) = 14.

Submission p. 2 · Guide §4
Why not 26

The parallel section takes 5 days, not 9.

Submission p. 2 · Guide §5
Time conventions

Day 0, relative days, and no calendar.

Guide §5 · Submission p. 1

Part 04

The backward pass and float

Holding the finish at day 22 and working back gives each activity’s late dates. The difference between late and early dates is float: zero for A, B, C, D, F and G, which confirms the critical path, and one day for E.

Open the case part
Backward-pass rules

The minimum successor late start, minus duration.

Guide §6 · Submission p. 2 · Deck p. 83
Backward check at C

LF(C) = min(9, 10) = 9, so LS(C) = 6.

Submission p. 2 · Guide §6
Total float

TF = LS − ES = LF − EF; zero except E.

Submission p. 2 · Guide §7 · Deck pp. 74, 79
Testing flexibility

One day of total and free float, shared.

Submission p. 2 · Guide §7 · Deck p. 76
Project float

Not calculable without an imposed date.

Guide §7 · Deck p. 74
The deck’s arithmetic slip

26 − 7 is 19, as the deck’s diagram shows.

Guide §7 · Deck p. 83

Part 05

What would change the answer?

The study guide changes one duration at a time to see how the answer responds. Lengthening E soon moves the critical path; shortening D helps only until E takes over; shortening E alone changes nothing. These are derived calculations, not changes to the submitted answer.

Open the case part
What-if calculations

Five single changes and their effect on duration.

Guide §8
Near-critical activities

Why a one-day margin still needs watching.

Guide §7 · Deck p. 76
Readiness at a merge

The unfinished dependency that controls the next activity.

Guide §8
Compression left out

Not added, because it would change the scenario.

Guide §9 · Deck pp. 87-92

Part 06

Building the two-page submission

The submission puts the answer first, then gives the model on page one and the evidence on page two. It goes beyond the two questions with a backward pass and float, and leaves out compression, resource limits and contingency on purpose.

Open the case part
The answer box

Critical path and duration at the top of page one.

Submission p. 1
Two-page structure

Model on page one, evidence on page two.

Guide §9 · Submission pp. 1-2
Scope of the analysis

Backward pass added; compression, resources and contingency left out.

Guide §9
Quick self-check

Five questions with short answers.

Guide §10
Reading map

Every deck citation is a PDF page of the 92-page deck.

Guide reading map

Source appendix

Where these documents need a careful reading

Read with care

Assumptions, not facts

The brief gives only activities, predecessors and durations. Finish-to-start links, no leads or lags, fixed durations, enough resources for D and E to overlap, day 0 and relative schedule days are the author’s stated assumptions.

Testing beside prototyping

On many real projects testing would follow prototype development. The brief makes testing depend only on design, and the answer keeps the table as given; the guide says a real team would validate that link.

More than the brief asks

The brief asks for the critical path and the duration. The backward pass, float, free float and the what-if table are added analysis; the what-if rows are not part of the submission at all.

Schedule days, not dates

No start date or working calendar is supplied, so day 22 is a schedule day, not a calendar date. The submission deadline is not the project’s finish date.

A coincidence of 26

Adding all seven durations gives 26 days, which is also the duration of the deck’s own worked example. The two numbers are unrelated. This is the case’s observation, not the documents’.

Compression is study context

Part 5 links the what-if results to Week 6’s compression methods for study. The submission and guide deliberately leave compression out.

The brief is in the session, not the library

The assignment brief was supplied with the documents and is reproduced here only for its task and activity table. Its dates and upload steps are left out.

Checked against the brief, the submission, the study guide and the Week 6 deck.

What not to take away

The case parts actively work against these misreadings:

  • The critical path is the single longest activity.
  • Critical means the most important or the hardest task.
  • Project duration is the sum of all activity durations.
  • Predecessor finish times are added at a merge.
  • The shorter path means the project could finish sooner.
  • Non-critical activities are optional.
  • One day of float can absorb a late start and a longer duration.
  • Speeding up any activity shortens the project.
  • Shortening the critical branch always saves the full amount.
  • Testing must follow development because it usually does.
  • Day 22 is a calendar date.
  • Project float can be calculated without an imposed finish date.

Study-guide synthesis; each item is addressed in the parts.