Where each part of this case comes from, and how its Week 6 page references stand against the course deck.
The three sources
The case reads the assignment brief, which supplies the activity table; a two-page submission that answers it; and the author's personal study guide, which explains the submission and is not part of the assessed work. Page and section numbers refer to those documents. Neither document is republished here.
Why there is a deck check
Both documents cite the Week 6 deck by PDF page. That deck is in this library, so every reference was checked against the actual pages and the result is published below. The check is this case's own work. Open the full case reference →
Case map · Brief, Submission, Guide and Deck
Case part
Submission
Guide
Course lessons applied
1 · The brief
p. 1: answer box, method and assumptions, inputs
§1-2, §9
Week 6: the critical path method, sequencing
2 · Reading the network
p. 1: network and path comparison
§3, §5
Week 6: sequencing, dependencies
3 · The forward pass
p. 2: rules, table, convergence at F
§4-5
Week 6: the critical path method, preparing the schedule
4 · Backward pass and float
p. 2: rules, table, backward check, testing flexibility
§6-7
Week 6: the critical path method
5 · What would change it
Not in the submission
§8
Week 6: the critical path method, schedule compression
6 · The two-page submission
pp. 1-2
§9-10
Week 6: the critical path method, summary
Read with careThe guide numbers its sections 1 to 10 and ends with an unnumbered reference reading map.
Week 6 references checked against the deck
Claim in the submission or guide
Deck
Result
Activity-on-node networks
p. 33
Matches
Finish-to-start links as the assumed relationship
p. 38
Matches: the deck calls finish to start the most common type; the choice to use it throughout is the author’s
No leads or lags
p. 49
Consistent with the deck’s definitions; the choice is the author’s
C diverges into D and E; F converges
p. 51
Matches
CPM finds the longest path, which governs duration
p. 72
Matches
Total float and project float definitions
p. 74
Matches
Near-critical activities need attention
p. 76
Matches
TF = LS − ES = LF − EF; free float = next ES − EF
p. 79
Matches
Forward-pass rules, starting at day 0
p. 81
Matches
Backward-pass rules
p. 83
Matches
The deck’s prose says 26 minus 7 is 7; the diagram shows 19
p. 83
Matches the Week 6 module’s own finding
Read with careNo contradiction with the deck was found. Every number in the case was also recomputed from the brief’s table, and all match both documents.
Part 01
The brief, and what it really tests
The assignment gives seven activities with their predecessors and durations, and asks for two results: the critical path and the total project duration. Underneath, it tests whether you can tell activities that must follow one another from activities that can run side by side.
Two results from seven activities, in a two-page document.
Brief
What the assignment tests
Sequential against concurrent activities; critical means effect on the finish.
Guide §1 · Deck p. 72
Why this approach
Path totals, then both passes, using Week 6 methods.
Guide §2 · Deck pp. 33, 72, 79, 81, 83
Assumptions
Finish to start, no leads or lags, fixed durations, resources for the overlap, day 0.
Submission p. 1 · Guide §3
Part 02
C splits, F joins: reading the network
The decisive detail is in the predecessor column. C is the only predecessor of both D and E, so the network splits after design; F needs both, so it joins again before implementation. That gives two complete paths, of 22 and 21 days.
Divergence and convergence in the assignment network.
Guide §3 · Deck p. 51
No D-to-E link
The supplied table is preserved; validate such links in real delivery.
Guide §3
Network and path comparison
The two complete paths and why the route through D governs.
Submission p. 1 · Guide §5
Assumptions behind the links
Finish to start, no leads or lags, resources for the overlap.
Submission p. 1 · Guide §3 · Deck pp. 38, 49
Part 03
The forward pass: 22 days, not 26
Moving from the start of the network to the end gives each activity’s early start and early finish. The only judgment call is at F, which must wait for the later of D and E. The pass ends at day 22, and it shows why simply adding every duration, 26 days, is wrong.
Holding the finish at day 22 and working back gives each activity’s late dates. The difference between late and early dates is float: zero for A, B, C, D, F and G, which confirms the critical path, and one day for E.
The study guide changes one duration at a time to see how the answer responds. Lengthening E soon moves the critical path; shortening D helps only until E takes over; shortening E alone changes nothing. These are derived calculations, not changes to the submitted answer.
The unfinished dependency that controls the next activity.
Guide §8
Compression left out
Not added, because it would change the scenario.
Guide §9 · Deck pp. 87-92
Part 06
Building the two-page submission
The submission puts the answer first, then gives the model on page one and the evidence on page two. It goes beyond the two questions with a backward pass and float, and leaves out compression, resource limits and contingency on purpose.
Critical path and duration at the top of page one.
Submission p. 1
Two-page structure
Model on page one, evidence on page two.
Guide §9 · Submission pp. 1-2
Scope of the analysis
Backward pass added; compression, resources and contingency left out.
Guide §9
Quick self-check
Five questions with short answers.
Guide §10
Reading map
Every deck citation is a PDF page of the 92-page deck.
Guide reading map
Source appendix
Where these documents need a careful reading
Read with care
Assumptions, not facts
The brief gives only activities, predecessors and durations. Finish-to-start links, no leads or lags, fixed durations, enough resources for D and E to overlap, day 0 and relative schedule days are the author’s stated assumptions.
Testing beside prototyping
On many real projects testing would follow prototype development. The brief makes testing depend only on design, and the answer keeps the table as given; the guide says a real team would validate that link.
More than the brief asks
The brief asks for the critical path and the duration. The backward pass, float, free float and the what-if table are added analysis; the what-if rows are not part of the submission at all.
Schedule days, not dates
No start date or working calendar is supplied, so day 22 is a schedule day, not a calendar date. The submission deadline is not the project’s finish date.
A coincidence of 26
Adding all seven durations gives 26 days, which is also the duration of the deck’s own worked example. The two numbers are unrelated. This is the case’s observation, not the documents’.
Compression is study context
Part 5 links the what-if results to Week 6’s compression methods for study. The submission and guide deliberately leave compression out.
The brief is in the session, not the library
The assignment brief was supplied with the documents and is reproduced here only for its task and activity table. Its dates and upload steps are left out.
Checked against the brief, the submission, the study guide and the Week 6 deck.
What not to take away
The case parts actively work against these misreadings:
The critical path is the single longest activity.
Critical means the most important or the hardest task.
Project duration is the sum of all activity durations.
Predecessor finish times are added at a merge.
The shorter path means the project could finish sooner.
Non-critical activities are optional.
One day of float can absorb a late start and a longer duration.
Speeding up any activity shortens the project.
Shortening the critical branch always saves the full amount.
Testing must follow development because it usually does.
Day 22 is a calendar date.
Project float can be calculated without an imposed finish date.
Study-guide synthesis; each item is addressed in the parts.