One change at a time
Each row below changes only the stated duration; every other duration and dependency stays as in the brief. The guide labels these as derived what-if calculations, not changes to the submitted answer.
| One change from the original | Project duration | What it demonstrates |
|---|---|---|
| E takes 5 days instead of 4 | 22 days | Both complete paths become equally long, and both are critical |
| E takes 6 days instead of 4 | 23 days | The route through E becomes the critical path |
| D takes 4 days instead of 5 | 21 days | Both branches take 4 days; both paths are critical |
| D takes 3 days instead of 5 | 21 days | E now governs; reducing D further gives no extra saving |
| E takes 3 days instead of 4 | 22 days | Finishing only the non-critical branch earlier does not shorten the project |
Reading the table
Three lessons come out of the five rows.
- Float runs out quickly One extra day on E uses all its float and makes two critical paths; a second day makes E the only critical branch.
- Shortening has a floor Cutting D helps only until it is no longer the longer branch. Below four days, E sets the pace and the saving stops.
- Off-path speed is wasted Finishing E earlier changes nothing, because F still waits for D.
The question at every merge
The guide closes this section with one practical question for delivery work: which unfinished dependency controls readiness for the next activity? In this exercise, completed testing does not let implementation start while prototype development is unfinished.
Key ideaAt a merge point, the latest predecessor is the one to watch, however far ahead the others are.
Where compression would come in
The what-if rows are sensitivity checks, not a plan to shorten the project. If the project did need to finish sooner, Week 6’s compression methods would apply, and they would act on the critical activities: fast tracking only works on discretionary dependencies, and crashing always adds cost.
Read with careThe submission deliberately leaves compression out, because adding it would change the supplied scenario rather than calculate it. This section connects the case to Lesson 7 for study only.
Key takeaways
- Change one duration at a time and recompute; the what-if rows are derived, not submitted.
- E has one day of float: one extra day ties the paths, two days move the critical path.
- Shortening D stops paying off once E becomes the longer branch.
- Speeding up a non-critical activity does not shorten the project.
- At a merge, ask which unfinished dependency controls readiness.