Schedule compression

When a schedule constraint cannot be met as things stand, the schedule can be compressed. Fast tracking overlaps critical activities and adds risk; crashing adds resources and always adds cost. The deck works through both and compares them with reducing scope and cutting quality.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Why compress a schedule

In many cases a schedule constraint cannot be met if things continue as they are. Either the schedule estimate was unrealistic, which the notes describe as a risk the project manager should identify early, or the project is already late.

Key ideaThe aim of compression is to change how the schedule is managed, not to change the schedule baseline.

Fast tracking

Fast tracking takes critical path activities that were planned one after another and performs them in parallel, for some or all of their duration.

  • Fast tracking often results in rework.
  • It usually increases risk.
  • It requires more attention to communication.
Fast tracking three critical activities · Source slide 88

As the deck draws it, B and C were planned one after another; fast tracked, both follow A and run side by side. The bar lengths are illustrative.

Read with careThis slide says fast tracking usually increases risk. The comparison table at the end of the lesson says it always adds risk. Both statements are shown.

What would you fast track?

The deck returns to the critical path example from Lesson 6, whose critical path is D, E, G, H, and C. Assuming all the dependencies are discretionary, it suggests two moves.

  • Activity H could be fast tracked by doing it at the same time as, or in parallel with, Activity G.
  • Activities C and H could also be fast tracked, by doing part of C concurrently with H.

Key ideaThe assumption matters. Only discretionary dependencies can be changed, as Lesson 3 explains; a mandatory dependency cannot be overlapped.

Crashing

Crashing adds or adjusts resources to compress the schedule while keeping the original project scope. By definition it always increases cost, and it may increase risk. It trades time for money.

A crashing example

Imagine a project with a project float of minus three months, and assume all the activities in the table are on the critical path. Which activities would you crash to save three months, and what would it cost?

Crash options · Source slide 91
ActivityOriginal duration (months)Crash duration (months)Time savingExtra cost ($)Cost per month ($)
J141224,0002,000
K98110,00010,000
N3211,0001,000
L7526,0003,000
M11839,0003,000

Read with careThe slide also lists each activity’s original cost (J 10,000, K 17,000, N 25,000, L 14,000, M 27,000) and crash cost (J 14,000, K 27,000, N 26,000, L 20,000, M 36,000).

Deck answerCrashing J and N is the least expensive way to remove the negative float. N saves one month for 1,000 dollars and J saves two months for 4,000 dollars, so the total cost of crashing is 5,000 dollars.

Key ideaStart with the lowest cost per month saved. Crashing M alone would also save three months, but for 9,000 dollars.

Four ways to recover time

The deck closes by comparing four compression options and their general impact on the project.

Characteristics of different schedule compression methods · Source slide 92
OptionGeneral impacts on the project
Fast trackAlways adds risk. May add management time for the project manager.
CrashAlways adds cost. May add management time for the project manager. May add risk.
Reduce scopeMay save cost, resources, and time. May negatively affect customer satisfaction.
Cut qualityMay save cost, resources, and time. May increase risk. Requires good metrics on current and desired levels of quality to be effective. May negatively affect customer satisfaction.

Key takeaways

  • Compress when a constraint cannot be met; change how the schedule is managed, not the baseline.
  • Fast tracking overlaps critical activities; it brings rework, risk, and more communication.
  • Only discretionary dependencies can be overlapped.
  • Crashing adds resources, always adds cost, and trades time for money; crash the cheapest month first.
  • Reducing scope or cutting quality can save time but may hurt customer satisfaction.

Study explanation based on the supplied Week 6: Scheduling source deck. Open the source notes above for slide-level traceability.

Your study checkpoint

Ready to continue?

Mark the lesson complete after you have read, reflected, and tested the main idea.

Next · Week 6 summary