Why compress a schedule
In many cases a schedule constraint cannot be met if things continue as they are. Either the schedule estimate was unrealistic, which the notes describe as a risk the project manager should identify early, or the project is already late.
Key ideaThe aim of compression is to change how the schedule is managed, not to change the schedule baseline.
Fast tracking
Fast tracking takes critical path activities that were planned one after another and performs them in parallel, for some or all of their duration.
- Fast tracking often results in rework.
- It usually increases risk.
- It requires more attention to communication.
As the deck draws it, B and C were planned one after another; fast tracked, both follow A and run side by side. The bar lengths are illustrative.
Read with careThis slide says fast tracking usually increases risk. The comparison table at the end of the lesson says it always adds risk. Both statements are shown.
What would you fast track?
The deck returns to the critical path example from Lesson 6, whose critical path is D, E, G, H, and C. Assuming all the dependencies are discretionary, it suggests two moves.
- Activity H could be fast tracked by doing it at the same time as, or in parallel with, Activity G.
- Activities C and H could also be fast tracked, by doing part of C concurrently with H.
Key ideaThe assumption matters. Only discretionary dependencies can be changed, as Lesson 3 explains; a mandatory dependency cannot be overlapped.
Crashing
Crashing adds or adjusts resources to compress the schedule while keeping the original project scope. By definition it always increases cost, and it may increase risk. It trades time for money.
A crashing example
Imagine a project with a project float of minus three months, and assume all the activities in the table are on the critical path. Which activities would you crash to save three months, and what would it cost?
| Activity | Original duration (months) | Crash duration (months) | Time saving | Extra cost ($) | Cost per month ($) |
|---|---|---|---|---|---|
| J | 14 | 12 | 2 | 4,000 | 2,000 |
| K | 9 | 8 | 1 | 10,000 | 10,000 |
| N | 3 | 2 | 1 | 1,000 | 1,000 |
| L | 7 | 5 | 2 | 6,000 | 3,000 |
| M | 11 | 8 | 3 | 9,000 | 3,000 |
Read with careThe slide also lists each activity’s original cost (J 10,000, K 17,000, N 25,000, L 14,000, M 27,000) and crash cost (J 14,000, K 27,000, N 26,000, L 20,000, M 36,000).
Deck answerCrashing J and N is the least expensive way to remove the negative float. N saves one month for 1,000 dollars and J saves two months for 4,000 dollars, so the total cost of crashing is 5,000 dollars.
Key ideaStart with the lowest cost per month saved. Crashing M alone would also save three months, but for 9,000 dollars.
Four ways to recover time
The deck closes by comparing four compression options and their general impact on the project.
| Option | General impacts on the project |
|---|---|
| Fast track | Always adds risk. May add management time for the project manager. |
| Crash | Always adds cost. May add management time for the project manager. May add risk. |
| Reduce scope | May save cost, resources, and time. May negatively affect customer satisfaction. |
| Cut quality | May save cost, resources, and time. May increase risk. Requires good metrics on current and desired levels of quality to be effective. May negatively affect customer satisfaction. |
Key takeaways
- Compress when a constraint cannot be met; change how the schedule is managed, not the baseline.
- Fast tracking overlaps critical activities; it brings rework, risk, and more communication.
- Only discretionary dependencies can be overlapped.
- Crashing adds resources, always adds cost, and trades time for money; crash the cheapest month first.
- Reducing scope or cutting quality can save time but may hurt customer satisfaction.