Good schedules start early
The previous lesson defined the project’s activities, which is essentially a detailed description of the scope in the form of a WBS. The WBS is the first step towards a schedule, because it supplies the schedule’s input. To go further, we need the order of those activities.
- Clear objectives
- Well-defined scope
- Accurate, detailed WBS
- Clear sequence
Key ideaDeveloping a good schedule starts long before scheduling happens. It can go back as far as the project definition phase.
Sequencing produces a network diagram
Sequencing means determining the precedence relationships, or prerequisites, among activities, then putting them in the order in which the work will be performed. The output is a network diagram showing the start, the order, and the finish of the project.
- In the activity-on-node representation, the start and finish are drawn as parallelograms, activities as rectangles, and precedence relationships as arrows.
- In the deck’s example, Activity A is the predecessor of Activities B and C, and Activities D and E are the successors of Activity B.
Read with careThe deck notes that the network diagram is just one method of displaying a schedule. Lesson 5 adds bar charts and milestone lists.
Activity on node and activity on arc
There is another way to draw the same logic. In the activity-on-arc representation the arcs, or arrows, are the activities, and the nodes mark where activities start and finish, which in a way shows the precedence relationships.
Activity on node
- Activities
- Rectangles, or nodes
- Arrows
- Precedence relationships
- Start and finish
- Parallelograms
- Deck example
- A precedes B and C; D and E follow B
Activity on arc
- Activities
- The arcs, or arrows
- Nodes
- The start and finish of activities
- Start and finish
- The first and last nodes
- Deck example
- A and B start first; C follows A, D follows B; C and D precede E
Which activities can start at once?
The deck asks which activities can start as soon as the project starts. In its diagram, Activities G and H come straight from the start and have no predecessors, so they can begin as soon as the project is initiated. They are the project’s starting activities.
Three precedence relationships
The deck describes three types of precedence relationship between a predecessor and its successor.
Finish to start
- Rule
- The predecessor finishes before the successor starts
- Example
- Dig the hole, then plant the tree
- Note
- The most common type
Start to start
- Rule
- The predecessor starts before the successor starts
- Example
- Design, then code; tubing, then wiring
Finish to finish
- Rule
- The predecessor finishes before the successor finishes
- Example
- Testing, then documentation
Finish to start
Finish to start is the most common relationship: the predecessor must be completely finished before the successor can start.
Deck exampleOn a pipeline, excavation has to be done before compaction begins. Or, more simply, the hole has to be dug before the tree is planted.
Start to start
In a start-to-start relationship, an activity has to be initiated before its successor can be initiated. The successor does not have to wait for the predecessor to finish.
Deck exampleCoding cannot start until design has started. Wiring cannot start unless tubing has started.
Read with careThe notes phrase the coding example as “we can’t start coding before designing the product”, which sounds like finish to start. The slide’s definition, and the wiring example, only need the predecessor to have begun. This lesson follows the definition.
Finish to finish
In a finish-to-finish relationship, an activity has to be completed before its successor can be completed. The two may run side by side, but they finish in order.
Deck exampleTesting has to finish before documentation is completed. Commissioning has to finish before the as-built drawings are completed.
Key takeaways
- The WBS is the input to the schedule; a good schedule depends on clear objectives, a well-defined scope, and a detailed WBS.
- Sequencing sets precedence relationships and produces a network diagram.
- Activity on node draws activities as boxes; activity on arc draws them as arrows between event nodes.
- Activities with no predecessors can start as soon as the project starts.
- Finish to start is the most common relationship; start to start and finish to finish link starts or finishes.