With the activities defined, the next step is their order. Sequencing sets the precedence relationships between activities and produces a network diagram, drawn either with activities on nodes or on arcs, and linked finish to start, start to start, or finish to finish.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Good schedules start early

The previous lesson defined the project’s activities, which is essentially a detailed description of the scope in the form of a WBS. The WBS is the first step towards a schedule, because it supplies the schedule’s input. To go further, we need the order of those activities.

Good schedules start long before scheduling · Source slides 31-32
  1. Clear objectives
  2. Well-defined scope
  3. Accurate, detailed WBS
  4. Clear sequence

Key ideaDeveloping a good schedule starts long before scheduling happens. It can go back as far as the project definition phase.

Sequencing produces a network diagram

Sequencing means determining the precedence relationships, or prerequisites, among activities, then putting them in the order in which the work will be performed. The output is a network diagram showing the start, the order, and the finish of the project.

  • In the activity-on-node representation, the start and finish are drawn as parallelograms, activities as rectangles, and precedence relationships as arrows.
  • In the deck’s example, Activity A is the predecessor of Activities B and C, and Activities D and E are the successors of Activity B.

Read with careThe deck notes that the network diagram is just one method of displaying a schedule. Lesson 5 adds bar charts and milestone lists.

Activity on node and activity on arc

There is another way to draw the same logic. In the activity-on-arc representation the arcs, or arrows, are the activities, and the nodes mark where activities start and finish, which in a way shows the precedence relationships.

Two ways to draw the network · Source slides 33-36

Activity on node

Activities
Rectangles, or nodes
Arrows
Precedence relationships
Start and finish
Parallelograms
Deck example
A precedes B and C; D and E follow B

Activity on arc

Activities
The arcs, or arrows
Nodes
The start and finish of activities
Start and finish
The first and last nodes
Deck example
A and B start first; C follows A, D follows B; C and D precede E

Which activities can start at once?

The deck asks which activities can start as soon as the project starts. In its diagram, Activities G and H come straight from the start and have no predecessors, so they can begin as soon as the project is initiated. They are the project’s starting activities.

Three precedence relationships

The deck describes three types of precedence relationship between a predecessor and its successor.

Three precedence relationships · Source slides 38-41

Finish to start

Rule
The predecessor finishes before the successor starts
Example
Dig the hole, then plant the tree
Note
The most common type

Start to start

Rule
The predecessor starts before the successor starts
Example
Design, then code; tubing, then wiring

Finish to finish

Rule
The predecessor finishes before the successor finishes
Example
Testing, then documentation

Finish to start

Finish to start is the most common relationship: the predecessor must be completely finished before the successor can start.

Deck exampleOn a pipeline, excavation has to be done before compaction begins. Or, more simply, the hole has to be dug before the tree is planted.

Start to start

In a start-to-start relationship, an activity has to be initiated before its successor can be initiated. The successor does not have to wait for the predecessor to finish.

Deck exampleCoding cannot start until design has started. Wiring cannot start unless tubing has started.

Read with careThe notes phrase the coding example as “we can’t start coding before designing the product”, which sounds like finish to start. The slide’s definition, and the wiring example, only need the predecessor to have begun. This lesson follows the definition.

Finish to finish

In a finish-to-finish relationship, an activity has to be completed before its successor can be completed. The two may run side by side, but they finish in order.

Deck exampleTesting has to finish before documentation is completed. Commissioning has to finish before the as-built drawings are completed.

Key takeaways

  • The WBS is the input to the schedule; a good schedule depends on clear objectives, a well-defined scope, and a detailed WBS.
  • Sequencing sets precedence relationships and produces a network diagram.
  • Activity on node draws activities as boxes; activity on arc draws them as arrows between event nodes.
  • Activities with no predecessors can start as soon as the project starts.
  • Finish to start is the most common relationship; start to start and finish to finish link starts or finishes.

Study explanation based on the supplied Week 6: Scheduling source deck. Open the source notes above for slide-level traceability.