Dependencies

The precedence relationship between two activities depends on the type of dependency between them. Dependencies are mandatory or discretionary by logic, and internal or external by the party requesting them; leads and lags fine-tune the links, and the result is a well-formed network diagram.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Two ways to classify a dependency

A dependency can be classified by its logic, mandatory or discretionary, or by the party requesting it, internal or external.

Types of dependencies · Source slides 43-44

By logic

Mandatory
Hard logic: the nature of the work, or a contract
Discretionary
Soft logic: the organization’s preferred way

By party

External
Required by a party outside the project, such as government or suppliers
Internal
Based on the project’s needs; the team controls it

The categories combine: a dependency can be mandatory and external, discretionary and internal, and so on.

Key ideaThe two categories are not mutually exclusive. A dependency can be mandatory and internal, discretionary and external, and so on.

Mandatory dependencies

A mandatory dependency, also called hard logic, is inherent in the nature of the work, or is required by a contract.

Deck exampleYou must install the steel before pouring the concrete. Contractually, a client may require design to be completed in a certain order.

Discretionary dependencies

A discretionary dependency, also called preferred, preferential, or soft logic, is the way the organization has chosen to have the work performed. There are other ways it could be done; this is simply the preferred one.

Deck exampleYou do not have to complete the design before starting construction, but some organizations choose a clean sequence.

Key ideaDiscretionary dependencies can be changed, which makes them very important when a schedule has to be compressed by fast tracking. Lesson 7 returns to this.

External and internal dependencies

Classified by the party requesting them, dependencies are either external or internal.

  • External Based on the needs or wishes of a party outside the project, such as the government or suppliers. Many jurisdictions require concrete testing before pouring, and supplier delivery schedules may dictate the order of installation.
  • Internal Based on the needs of the project itself. The project team can control them.

Leads and lags

Sometimes a relationship does not fit the three main types neatly, so activities are linked with leads and lags.

  • A lead lets an activity start before its predecessor is completed. The slide’s example is starting web design five days before the database is completed; the notes’ example is starting construction five days before design is finalized.
  • A lag is waiting time inserted between activities, for example between pouring the concrete and installing the frame. Lags may account for uncertainty or for the nature of the work.

Key ideaEarly in a project, activity durations, leads, and lags may all be uncertain, because little is yet known about the work.

A well-formed network diagram

Defining and sequencing produce the project schedule network diagram: an image of the flow of project activities in the logical order in which they will be performed. The deck gives some good practices.

  • Every activity after the start activity is connected to at least one predecessor.
  • Every activity before the finish activity is connected to at least one successor.
  • When a schedule becomes complex, always use electronic scheduling software.

Path convergence and path divergence

When an activity has two or more activities directly preceding it, that is path convergence. When an activity has two or more successors directly following it, that is path divergence.

Path convergence and path divergence · Source slide 53

Path convergence

  • Two or more activities directly precede one activity
  • Paths merge into it

Path divergence

  • Two or more activities directly follow one activity
  • Paths split from it

Key takeaways

  • Dependencies are mandatory or discretionary by logic, and internal or external by party; the two categories combine.
  • Mandatory dependencies come from the nature of the work or a contract; discretionary ones are the organization’s preference.
  • Discretionary dependencies can be changed, which is what makes fast tracking possible.
  • A lead lets a successor start early; a lag inserts waiting time.
  • Every activity needs a predecessor after the start and a successor before the finish; complex schedules need software.

Study explanation based on the supplied Week 6: Scheduling source deck. Open the source notes above for slide-level traceability.