Project Management · Module 6Lesson 1

Study explanation · Lesson 01 · 22 min

Scheduling basics

A schedule starts with a plan for managing it and a breakdown of the work. This lesson covers the schedule management plan, the five-step scheduling process, the work breakdown structure, work packages, milestones, and rolling wave planning.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Why time is so hard to manage

Time is a key success factor on projects, and making sure a project finishes on time is one of the project manager’s responsibilities. The deck calls it the hardest outcome to manage on capital projects: most of them slip their schedules, some by more than a year.

Key ideaOne essential criterion for judging a project manager is the project’s deviation from its planned schedule, or from the schedule set when the charter was approved. So the schedule must first be realistic, so that the team can actually meet it.

The schedule management plan

Before developing the schedule itself, the project needs an approach for managing it, decided firmly early in the project. The notes say it should be cast in stone early on. The plan can be formal or informal, but it is typically part of the overall project management plan.

  • It outlines the scheduling methodology, including the tools or software to be used.
  • It explains how the schedule baseline will be developed and controlled.
  • It defines the measures of variance, and the thresholds that trigger corrective action.
  • It specifies how often schedule reports are issued.
  • For adaptive or agile projects, it sets the length of iterations and the release timelines.

Read with careWhat is fixed early is the approach to managing the schedule. Lesson 5 says the schedule itself is dynamic and preparing it is iterative, while the approved baseline changes only through change control.

Scheduling is a process

Generating a project plan is a phased process. The deck names five steps. First define the activities, then sequence them by their precedence relationships, then estimate each activity’s duration, then schedule the project electronically to get the overall duration. Scheduling work does not end when the schedule is ready: it is controlled throughout execution.

Scheduling projects: a process · Source slides 9-10
  1. DefiningThe required activities
  2. SequencingTheir precedence relationships
  3. EstimatingEach activity’s duration
  4. SchedulingThe overall duration and dates
  5. ControllingThroughout execution

Key ideaThe notes describe schedules as the final outcome of project planning.

Planning is not scheduling

The two are related but different, and they happen in sequence. Planning determines the ways, the means, and the steps needed to carry out a job. Scheduling shows those steps on a calendar.

Deck exampleTo build a flat, the plan is to excavate, erect the foundation, build the superstructure, and then do the electrics and the HVAC. The schedule puts those steps on dates.

Key ideaPlanning and costing, on the other hand, run in parallel and are closely linked. Unit prices are by-products of the planning process. In the notes’ words, the money available decides how fast the work can go, and the number of workers needed affects the budget.

Breaking down the work

Defining activities starts with a breakdown of the work, and the deck gives three ways to do it. The breakdown identifies the project’s activities, and estimating cost then means allocating resources to those activities, which is why planning and costing go together.

Three ways to break down the work · Source slides 13-14

By area

  • Area-based supervision coordinates the crafts within each area
  • A water network broken down by province

By components

  • A water project split into the pipeline and the pump station

By trade

  • Electrical, mechanical, waterproofing, curtain wall, finishing
  • Plumbing and civil works

Breaking down the work identifies the activities; estimating cost then allocates resources to them. Planning and costing are intimate processes.

Where to stop the breakdown

How far should the project be broken down, and which activities belong in the programme? Normally, the deck says, those with a significant impact on cost.

Deck exampleIf the budget for a trip is 1,000 dollars, activities consuming 200 dollars are significant, and activities consuming 20 dollars are not. On a million-dollar project you care about activities costing tens of thousands of dollars, not tens or hundreds.

The work breakdown structure

A work breakdown structure, or WBS, breaks a project down into a hierarchy of manageable chunks of work. It adds logic to managing the work, and most importantly it is a visual way of representing the project.

Key ideaVisual plus hierarchical makes the project easier to manage, and means activities are not forgotten.

Work packages

A work package is the lowest level of the WBS. As a ballpark, it should not take more than two weeks of work, which is 80 working hours or less.

  • Every work package has an owner, who is part of the project team.
  • The owner is responsible for delivering the work and completing it successfully.

Guidelines for developing a WBS

There is no ideal way to develop a WBS, but the deck offers four good practices.

  1. Build it top down, not bottom up.
  2. Do not exceed about five levels.
  3. Identify a work package owner for each WBS item.
  4. Align it with the project charter.

Key ideaThe notes put the last point simply: the WBS does not exist in a vacuum. It has to align with the project’s objectives and its charter.

Milestones

Milestones are significant events within the project schedule. They are not work activities and they have no duration. Think of them as checkpoints, or major steps the project has to reach.

  • Slide examples: complete design, a phase gate, complete a floor.
  • Notes examples: 90 percent design complete, finalize the foundation, align on the user interface.
  • A manager may insert milestones to measure progress. If the milestone date arrives and some of its work is not complete, the project is late.

Two example breakdowns

The deck shows an outline WBS organized by zones. WBS 1 is Zone 1, a residential building with twelve floors, two basements, and a parking area. Its scope includes electrical systems, meaning low-voltage wiring, data wiring, and gas piping, and mechanical systems, meaning HVAC and plumbing. WBS 2 and WBS 3 cover Zones 2 and 3. A second example breaks down the planning of a charity cycling event.

A WBS for event planning · Source slide 27

Cycling event

  1. Itinerary
    • TransportationBook tickets and acquire travel cards · research means of transportation
    • RouteResearch possible routes · check weather conditions · route established
    • AccommodationSearch for available hotels · compare offers · confirm bookings
  2. Fund-raise
    • Online crowd fundingResearch sites · evaluate options · page confirmed · page promotion
    • Participation feeDebate and decide the sum · sum confirmed · collect the money
    • Refreshment boothsResearch and rent · prepare menu · buy supplies
  3. Participants
    • RecruitmentContact WUSC · create invitations · invitations sent · confirm participants

Three levels below the event itself: the main areas, their deliverables, and the work under each one.

Rolling wave planning

On a project that involves new technology or innovation, the team may not know every activity in advance. It develops higher-level plans first and adds detail as the work progresses. This is rolling wave planning, a form of progressive elaboration: activities are planned to the detail needed just before that part of the project starts, and iterations may add activities or develop them further.

Read with careThe same slide insists that, whatever the management philosophy, the scope must be known before the project starts; the notes say it must be closed. Read the two together: the activities can grow as the project is elaborated, but the scope boundary should not.

Key takeaways

  • Most capital projects slip; a project manager is judged on deviation from the planned schedule, so the schedule must be realistic.
  • The schedule management plan sets the method, tools, baseline control, variance thresholds, reporting frequency, and iteration length.
  • Scheduling runs in five steps: defining, sequencing, estimating, scheduling, and controlling.
  • Planning sets the steps; scheduling puts them on a calendar; planning and costing run in parallel.
  • A WBS is top down, about five levels at most, owned, and aligned with the charter; work packages take two weeks or less.
  • Milestones have no duration; rolling wave planning details activities just in time, within a known scope.

Study explanation based on the supplied Week 6: Scheduling source deck. Open the source notes above for slide-level traceability.