Project Management · Module 6 reference

Glossary

Short, source-grounded definitions to use alongside the learning path.

Schedule management plan

The approach to managing the schedule, set early: methodology, tools, baseline development and control, variance thresholds, reporting frequency, and iteration length.

Review Lesson 1
Planning

Determining the ways, means, and steps required to carry out a job.

Review Lesson 1
Scheduling

Showing on a calendar the steps that result from planning.

Review Lesson 1
Work breakdown structure (WBS)

A visual, hierarchical breakdown of the project into manageable chunks of work.

Review Lesson 1
Work package

The lowest level of the WBS, roughly two weeks or 80 hours of work or less, with an owner on the project team.

Review Lesson 1
Milestone

A significant event in the schedule, not a work activity, with no duration.

Review Lesson 1
Rolling wave planning

A form of progressive elaboration in which activities are planned in detail just before that part of the project starts.

Review Lesson 1
Network diagram

An image of the project’s activities in the logical order in which they will be performed.

Review Lesson 2
Activity on node

A network diagram in which activities are boxes and arrows show precedence.

Review Lesson 2
Activity on arc

A network diagram in which arrows are activities and nodes mark their start and finish.

Review Lesson 2
Finish to start

The most common relationship: the predecessor finishes before the successor starts.

Review Lesson 2
Start to start

The predecessor must start before the successor can start.

Review Lesson 2
Finish to finish

The predecessor must finish before the successor can finish.

Review Lesson 2
Mandatory dependency

Hard logic: inherent in the nature of the work, or required by a contract.

Review Lesson 3
Discretionary dependency

Soft or preferential logic: the organization’s chosen way of working, which can be changed, for example to fast track.

Review Lesson 3
External dependency

A dependency based on the needs of a party outside the project, such as the government or suppliers.

Review Lesson 3
Internal dependency

A dependency based on the needs of the project, which the team can control.

Review Lesson 3
Lead

Allowing an activity to start before its predecessor is completed.

Review Lesson 3
Lag

Waiting time inserted between activities.

Review Lesson 3
Path convergence and divergence

An activity with two or more direct predecessors, or with two or more direct successors.

Review Lesson 3
Relative sizing

Estimating from previously completed work, often in story points, on adaptive projects.

Review Lesson 4
Parametric estimation

Estimating with equations from historical records: regression, learning curves, or heuristics.

Review Lesson 4
Analogous estimation

A rough, top-down estimate of the overall duration from similar historical projects.

Review Lesson 4
Bottom-up estimation

Detailed estimates for each part of the WBS, rolled up into control accounts and the project estimate.

Review Lesson 4
Schedule model

All the data needed to calculate the schedule: activities, durations, dependencies, leads, and lags.

Review Lesson 5
Schedule baseline

The approved schedule, part of the project management plan, changed only through change management.

Review Lesson 5
Resource calendar

A record of when resources are available.

Review Lesson 5
Critical path

The longest path through the network diagram, which governs the project’s duration; its activities have zero float.

Review Lesson 6
Total float

How long an activity can be delayed without delaying the project end date or a milestone: LS − ES, or LF − EF.

Review Lesson 6
Free float

How long an activity can be delayed without delaying its successor’s early start: next ES − current EF.

Review Lesson 6
Project float

How long the project can be delayed without missing its imposed completion date.

Review Lesson 6
Negative float

A sign that the project is already late, or that its completion constraints are unrealistic.

Review Lesson 6
Forward and backward pass

Calculating early dates from the start, then late dates from the end, to find each activity’s float.

Review Lesson 6
Fast tracking

Performing critical activities planned in sequence in parallel; often adds rework and risk.

Review Lesson 7
Crashing

Adding or adjusting resources to compress the schedule while keeping scope; always adds cost.

Review Lesson 7