Activity estimation

The goal of scheduling is the project’s duration, so each activity needs a duration estimate. The deck covers relative sizing, one-point estimates, parametric estimation, analogous top-down estimates, and bottom-up estimates built from the WBS.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Estimating means uncertainty

So far the module has defined and sequenced activities. But an ultimate goal of scheduling is the duration of the project, which needs a duration for each activity. The deck notes that estimation involves uncertainty, and uncertainty implies probability.

Read with careThe deck promises some statistics before the estimating slides, but none follow, and three-point estimating is later named without a formula. This lesson adds no formula of its own.

Methods from top down to bottom up

The methods differ in where the estimate starts and how much detail they need. This study-guide view arranges them from the roughest, earliest estimate to the most detailed one.

Estimation methods · Study-guide arrangement of source slides 56-62

Rough, early, top down

  1. AnalogousWhole-project duration from similar projects
  2. Relative sizingStory points from past work, on adaptive projects
  3. One-point and parametricOne figure per activity, or an equation from history
  4. Bottom upEvery work package, rolled up

Detailed, from the WBS

Relative sizing

Relative sizing is common on adaptive projects, not on predictive ones. It is not an absolute estimate: it uses previously completed work to estimate future work. The notes say adaptive projects use story points rather than absolute time frames.

Deck exampleThe notes compare it to giving directions to a friend.

One-point estimating

One-point estimating gives a single estimate for each activity, based on historical information or expert judgement. It can be used on both predictive and adaptive projects.

Deck exampleAn electrical engineer can estimate the timeline for a 120 square metre solar system, either as a whole or for its parts, such as building the frame and erecting the panels.

Parametric estimation

Parametric estimation develops mathematical equations from historical records. The notes say the details are beyond the scope of the module, but name three methods.

  • Regression analysis An equation fitted to historical data.
  • Learning curve If the first floor took ten days, how long will the hundredth take?
  • Heuristics A rule of thumb, such as: design always takes 15 percent of the overall project duration.

Analogous, or top-down, estimation

Analogous estimation sets the overall duration of the project from similar historical projects, and then uses it to evaluate single activities. The deck says it is done by project sponsors, as a rough estimate early on, and its accuracy depends on the quality of the data.

Deck exampleI completed a similar plant within six months, so my project will take roughly the same time.

Bottom-up estimation

Bottom-up estimation creates detailed estimates for each component of an activity or work package, so an accurate WBS is essential. It begins at the most granular level, then rolls the estimates up into control accounts, and the control accounts up into the overall project estimate.

  • Within it, the individual estimates can be single-point estimates, three-point estimates, or parametric estimates, depending on the activity.

Read with careLesson 1 says the WBS itself is built top down. Bottom-up estimation is a different step: it starts from the WBS’s lowest level once the WBS exists.

Key takeaways

  • Estimating durations involves uncertainty.
  • Relative sizing uses past work and story points on adaptive projects; one-point estimating gives one figure per activity.
  • Parametric methods include regression, learning curves, and heuristics.
  • Analogous estimates are rough, top-down, early, and only as good as their data.
  • Bottom-up estimates need an accurate WBS and roll up through control accounts.

Study explanation based on the supplied Week 6: Scheduling source deck. Open the source notes above for slide-level traceability.

Your study checkpoint

Ready to continue?

Mark the lesson complete after you have read, reflected, and tested the main idea.

Next · Lesson 5