What the critical path method does
The critical path method, or CPM, determines the longest-duration path through the network diagram, together with the earliest and latest each activity can start and finish. The aim is to find the critical path, the path that governs the duration of the project.
Key ideaA critical activity list gathers the critical activities: those that cannot be delayed without affecting the whole project.
The concept of float
Float, also called slack, is the amount of flexibility in the schedule. The deck names three types.
- Total float The primary type. How long an activity can be delayed without delaying the project end date or an intermediate milestone, within any imposed schedule constraints.
- Free float How long an activity can be delayed without delaying the early start of its successor or successors, within any imposed constraints.
- Project float How long the project can be delayed without missing the completion date imposed by the customer or management, or committed earlier by the project manager. The deck says it is also called positive float.
Key ideaWhen a project has negative float, it is either already late, or the constraints on its completion are unrealistic, for example a date set by management that can never be met.
Float and the critical path
The deck links float to the critical path in four points.
- Activities on the critical path have zero float.
- A critical activity that is delayed, or that has an imposed completion date, can produce negative float.
- Take care of near-critical activities, because the critical path can easily shift.
- Float is an asset to the project, a kind of fluff around the schedule that can be used to re-optimize resources.
How each activity is drawn
Network diagrams use a standard notation for each activity. The duration sits above the node and the activity name in the middle, with the float beneath it. The early start and early finish go in the top corners, and the late start and late finish in the bottom corners.
ES and EF are the early start and early finish; LS and LF are the late start and late finish.
The float formulas
Total float can be calculated in two equivalent ways. Free float has a single formula.
- Total float = late start − early start.
- Total float = late finish − early finish.
- Free float = early start of the next activity − early finish of the current activity.
The worked example
The deck’s example has eight activities. Activities A and D have no predecessors. E can start only when D is complete. F needs both D and A. G follows E and F, B follows F, H follows G, and C follows H. Activities B and C have no successors, so both lead to the end.
| Activity | Duration (days) | Predecessors |
|---|---|---|
| D | 4 | Start |
| A | 3 | Start |
| E | 9 | D |
| F | 8 | D and A |
| G | 4 | E and F |
| B | 4 | F |
| H | 2 | G |
| C | 7 | H |
The forward pass
The forward pass finds the earliest each activity can finish. An activity’s early start is the largest early finish among its predecessors, and its early finish is its early start plus its duration.
- A has no predecessors, so it starts at day 0 and finishes at day 3. D starts at 0 and finishes at 4.
- F needs both A and D. A finishes at day 3 and D at day 4, so F cannot start before day 4. With eight days’ duration, it finishes at day 12.
- E runs from 4 to 13. G waits for E and F, so it starts at 13, the later of 13 and 12, and finishes at 17.
- B runs from 12 to 16, H from 17 to 19, and C from 19 to 26.
Key ideaThe earliest the project can end is day 26.
The backward pass
The backward pass works from the end back to the start. An activity’s late finish is the smallest late start among its successors, and its late start is its late finish minus its duration.
- B and C have no successors, so the project’s 26 days become their late finish.
- C’s late start is 26 minus 7, which is 19. B’s late start is 26 minus 4, which is 22.
- Working back, H’s latest start is 17 and G’s is 13.
- F has two successors, G and B, with late starts of 13 and 22. So F can finish no later than day 13 without delaying a successor, and its late start is 5.
- E’s late dates are 4 and 13, D’s are 0 and 4, and A’s are 2 and 5.
Read with careThe notes say C’s late start is “26 minus 7 which is 7”; the diagram shows 19, which is correct. The notes also say F can finish without delaying its predecessors, where successors is meant. This lesson uses the diagram’s numbers.
Float and the critical path in the example
Subtracting early dates from late dates gives each activity’s total float. The activities with zero float form the critical path: D, E, G, H, and C. Their latest starts equal their earliest starts. Activity A has a float of 2, F a float of 1, and B a float of 10.
Critical path · zero float
- Start
- 40D4004After Start
- 94E134013After D
- 413G1713017After E and F
- 217H1917019After G
- 719C2619026After H, then End
- End · day 26
Off the critical path
- 30A3225After Start
- 84F125113After D and A
- 412B16221026After F, then End
Each node shows ES and EF on top, LS and LF below, and total float in the middle. The links are those of the deck’s diagram: F waits for both D and A, and G waits for both E and F.
| Activity | Duration | ES | EF | LS | LF | Total float | Free float |
|---|---|---|---|---|---|---|---|
| D | 4 | 0 | 4 | 0 | 4 | 0 | 0 |
| A | 3 | 0 | 3 | 2 | 5 | 2 | 1 |
| E | 9 | 4 | 13 | 4 | 13 | 0 | 0 |
| F | 8 | 4 | 12 | 5 | 13 | 1 | 0 |
| G | 4 | 13 | 17 | 13 | 17 | 0 | 0 |
| B | 4 | 12 | 16 | 22 | 26 | 10 | 10 |
| H | 2 | 17 | 19 | 17 | 19 | 0 | 0 |
| C | 7 | 19 | 26 | 19 | 26 | 0 | 0 |
Read with careThe deck gives total float only. The free float column applies its formula: A finishes at day 3 and F starts at day 4, so A has 1 day of free float but 2 of total float.
Watching the near-critical path
Adding up the durations along each route through the example shows why the deck warns about near-critical activities. This is a study-guide calculation using the example’s own numbers.
- D, E, G, H, C: 26 days, the critical path.
- D, F, G, H, C: 25 days, only one day shorter.
- A, F, G, H, C: 24 days.
- D, F, B: 16 days, and A, F, B: 15 days.
Key ideaIf F slips by two days, the second route becomes 27 days long and the critical path shifts to run through F. Float is an asset, but a thin one here.
Key takeaways
- The critical path is the longest path through the network and governs the project’s duration.
- Total float is LS − ES or LF − EF; free float is the next activity’s ES − the current EF.
- Forward pass: ES = the largest predecessor EF, EF = ES + duration. Backward pass: LF = the smallest successor LS, LS = LF − duration.
- Critical activities have zero float; negative float means the project is late or its constraints are unrealistic.
- In the example the project takes 26 days, the critical path is D, E, G, H, C, and F is near critical.