Project Management · Module 6Applied casePart 4

Applied case · Part 04 · 15 min

The backward pass and float

Holding the finish at day 22 and working back gives each activity’s late dates. The difference between late and early dates is float: zero for A, B, C, D, F and G, which confirms the critical path, and one day for E.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Two rules, working backwards

Late finish is the latest an activity can complete without moving the project finish; late start subtracts its duration. G’s late finish is set to day 22, the calculated earliest finish. At a split, protect the earliest late start among the successors.

  1. Late finish = the smallest late start among the immediate successors.
  2. Late start = late finish − duration.

Activity by activity, from G back to A

The backward pass runs in the opposite direction to the forward pass, from closure back to initiation.

The backward pass · Guide §6
ActivityLate finish: reason or calculationLS
G22: preserve the calculated project finish22 − 2 = 20
F20: G must start by 2020 − 6 = 14
D14: F must start by 1414 − 5 = 9
E14: F must start by 1414 − 4 = 10
Cmin(9, 10) = 9: protect both D and E9 − 3 = 6
B6: C must start by 66 − 4 = 2
A2: B must start by 22 − 2 = 0

Key ideaAt C the backward pass takes the minimum, because C must finish in time for D, the successor that has to start earliest.

Float confirms the critical path

Total float is how long an activity can be delayed without delaying the project end. Week 6 calculates it as late start minus early start, or late finish minus early finish.

The assignment network after both passes · Submission p. 2, recomputed

Critical path · zero float

  1. Start
  2. Initiation · first
  3. Requirements · after A
  4. Design · after B
  5. Prototype · after C
  6. Implementation · after D and E
  7. Closure · after F
  8. End · day 22

Off the critical path

  1. Testing · after C, then F

Each node shows ES and EF on top, LS and LF below, and total float in the middle. E is the only activity with float: one day, between its early window of 9 to 13 and its late window of 10 to 14.

Schedule calculations · Submission p. 2
ActivityDurationESEFLSLFTotal floatCritical?
A202020Yes
B426260Yes
C369690Yes
D59149140Yes
E491310141No
F6142014200Yes
G2202220220Yes

Key ideaThe zero-float chain is A → B → C → D → F → G, the same answer the path totals gave.

E’s one day

For E, 10 − 9 = 14 − 13 = 1 day of total float. Its early window is days 9 to 13 and its late window is days 10 to 14; either lets F start at day 14. E is not critical, but a delay beyond that one day would move the finish, which is why the deck warns about near-critical activities.

  • The day is a shared allowance. E cannot start one day late and also take one day longer: together, those push E to day 15 and the project to day 23, unless time is recovered elsewhere.
  • E also has one day of free float: F’s early start minus E’s early finish, 14 − 13 = 1. It is not an extra day on top of the total float.

The float that cannot be calculated

Project float measures how long the project can slip before missing a completion date imposed by the customer or management. The brief imposes no completion date, so that separate measure cannot be calculated here.

A slip in the deck, checked

The deck’s backward-pass notes say that 26 minus 7 is 7; the arithmetic gives 19, which matches the deck’s own diagram. The guide notes the slip and applies the printed rule, late start = late finish − duration, to the assignment’s own data.

Read with careThe Week 6 module flags the same slip in its source guide. The assignment’s numbers do not depend on it.

Key takeaways

  • LF = the smallest successor LS; LS = LF − duration; start the pass from the project finish.
  • At a split, take the minimum, so the predecessor protects the most urgent successor.
  • A, B, C, D, F and G have zero float, confirming the critical path.
  • E has one day of total float and one of free float, and the day can be used only once.
  • Without an imposed completion date, project float cannot be calculated.

Study explanation of an academic critical path submission and its study guide, read against the supplied Week 6: Scheduling course deck. Open the source notes above to see which document each claim comes from.