The answer first
The first lines of the submission state the two results the brief asked for, before any working: the critical path, A → B → C → D → F → G, and the total project duration, 22 days.
Key ideaAn assessor can find the answer without reading the method, and then check the method against it.
Page one defines the model
Page one sets out everything a reader needs to reproduce the answer.
- Method and assumptions: CPM with a forward pass, a backward pass and total float, and the stated modelling assumptions.
- Activity inputs: the brief’s table, unchanged.
- Network and path comparison: the split and the merge, the critical activities outlined, and the two complete paths with their totals.
Page two gives the evidence
Page two shows the calculations that support the answer.
- The forward-pass, backward-pass and float rules, each cited to the deck.
- The schedule table: duration, ES, EF, LS, LF, total float and critical status for every activity.
- Key calculations: the convergence at F, the backward check at C, and E’s one day of flexibility.
- Interpretation and conclusion, including why adding all durations gives the wrong answer.
Beyond the brief, and where it stops
The brief asks only for the critical path and the duration. The backward pass and float are included to deepen the analysis. Schedule compression, new resource limits and extra contingency are left out, because they would change the supplied scenario rather than calculate it.
Applied choiceBoth the extra depth and its limits are the author’s choices, within the two-page limit. Each citation points to a PDF page of the Week 6 deck.
Five questions to check any answer
The guide ends with a quick self-check. Each question has a short answer, and each one catches a common mistake.
- Can E start after C, before D finishes? Yes. Its only listed predecessor is C.
- Why does F start at day 14, not 13? It waits for the later of D’s and E’s finishes.
- Why 22 days, not 26? D and E overlap instead of being added in sequence.
- What makes the path critical? It is the longest complete path, and every activity on it has zero total float.
- Does non-critical mean optional? No. E is required work, with only one day of flexibility.
Key takeaways
- State the answer first, then the model, then the evidence.
- Page one: method, assumptions, inputs, network and path totals. Page two: rules, the schedule table, key calculations and the conclusion.
- The backward pass and float go beyond the brief; compression and contingency are left out on purpose.
- Five quick questions catch the common mistakes.