Project Management · Module 06 · Applied case

The critical path, calculated

Seven activities, one split and one merge: how a 22-day answer is found, checked and explained.

A two-page critical path submission and its study guide, read part by part: what the brief really tests, how the network splits and joins, the forward pass that gives 22 days rather than 26, the backward pass and float that confirm the critical activities, what would change the answer, and how the submission is built. Every assumption the author made is marked as an applied choice.

The calculation, part by part

Watch seven activities become one answer.

Open case sources
01The briefThe assignment gives seven activities with their predecessors and durations, and asks for two results: the critical path and the total project duration. Underneath, it tests whether you can tell activities that must follow one another from activities that can run side by side.11 min02Reading the networkThe decisive detail is in the predecessor column. C is the only predecessor of both D and E, so the network splits after design; F needs both, so it joins again before implementation. That gives two complete paths, of 22 and 21 days.13 min03The forward passMoving from the start of the network to the end gives each activity’s early start and early finish. The only judgment call is at F, which must wait for the later of D and E. The pass ends at day 22, and it shows why simply adding every duration, 26 days, is wrong.14 min04Backward pass and floatHolding the finish at day 22 and working back gives each activity’s late dates. The difference between late and early dates is float: zero for A, B, C, D, F and G, which confirms the critical path, and one day for E.15 min05What would change itThe study guide changes one duration at a time to see how the answer responds. Lengthening E soon moves the critical path; shortening D helps only until E takes over; shortening E alone changes nothing. These are derived calculations, not changes to the submitted answer.11 min06The two-page submissionThe submission puts the answer first, then gives the model on page one and the evidence on page two. It goes beyond the two questions with a backward pass and float, and leaves out compression, resource limits and contingency on purpose.10 min