Project Management · Module 6Applied casePart 1

Applied case · Part 01 · 11 min

The brief, and what it really tests

The assignment gives seven activities with their predecessors and durations, and asks for two results: the critical path and the total project duration. Underneath, it tests whether you can tell activities that must follow one another from activities that can run side by side.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

The assignment in one line

Using the activity table provided, calculate the critical path, which the brief defines as the longest sequence of dependent tasks, and the total project duration. The answer is submitted as a two-page document.

The activity table supplied with the assignment · Brief
ActivityPredecessor(s)Duration (days)
A · Project initiationNone2
B · Requirement analysisA4
C · DesignB3
D · Prototype developmentC5
E · TestingC4
F · Final implementationD and E6
G · Project closureF2

Key ideaThe study guide names the real test: distinguishing activities that must happen one after another from activities that can happen at the same time.

What “critical” means

The critical path is the longest complete chain of dependent activities, and it determines the earliest finish of the whole project, because all the required work must be completed. The guide adds a warning that is easy to miss.

  • “Critical” describes the effect on the finish date, not how important or technically difficult a task feels.
  • F is the longest single activity, at six days, but the answer must be a complete path from initiation to closure, not F alone.

Why the Week 6 method fits

The activities and durations are already supplied, so there is no need to invent a work breakdown structure or to re-estimate anything. Week 6’s activity-on-node networks, forward and backward passes, and float answer the two questions directly.

  • Comparing the totals of the complete paths gives the answer quickly.
  • The forward pass verifies when each activity can start.
  • The backward pass and float explain why those activities are critical.

Key ideaShowing all three turns the submission into a worked analysis rather than an unsupported final number.

Given, and assumed

The brief gives the activities, their predecessors and their durations, and nothing else. Everything in the right-hand column below had to be assumed, and the submission states each assumption on its first page.

What the brief gives, and what the answer assumes · Brief · Submission p. 1
Given by the briefAssumed by the author
Seven activities, A to GEvery link is finish to start
Each activity’s predecessorsNo leads or lags
Each activity’s duration in daysDurations are fixed
Two questions: the critical path and the durationEnough resources for D and E to run at the same time
A two-page submissionTime starts at day 0, in relative schedule days, with no extra activities or contingency

Applied choiceThese assumptions are the author’s, stated so a reader can see exactly which model was solved. Finish to start is the deck’s most common relationship, but the brief itself does not name a link type.

Key takeaways

  • The brief asks for two results: the critical path and the total duration.
  • The critical path is the longest complete chain of dependent activities; it sets the earliest finish.
  • “Critical” is about the finish date, not about importance or difficulty.
  • The brief gives activities, predecessors and durations; link types, resources and the time convention are assumptions.

Study explanation of an academic critical path submission and its study guide, read against the supplied Week 6: Scheduling course deck. Open the source notes above to see which document each claim comes from.

Your study checkpoint

Ready to continue?

Mark the part complete once you have read it, checked its sources, and tested the idea against a project of your own.