The assignment in one line
Using the activity table provided, calculate the critical path, which the brief defines as the longest sequence of dependent tasks, and the total project duration. The answer is submitted as a two-page document.
| Activity | Predecessor(s) | Duration (days) |
|---|---|---|
| A · Project initiation | None | 2 |
| B · Requirement analysis | A | 4 |
| C · Design | B | 3 |
| D · Prototype development | C | 5 |
| E · Testing | C | 4 |
| F · Final implementation | D and E | 6 |
| G · Project closure | F | 2 |
Key ideaThe study guide names the real test: distinguishing activities that must happen one after another from activities that can happen at the same time.
What “critical” means
The critical path is the longest complete chain of dependent activities, and it determines the earliest finish of the whole project, because all the required work must be completed. The guide adds a warning that is easy to miss.
- “Critical” describes the effect on the finish date, not how important or technically difficult a task feels.
- F is the longest single activity, at six days, but the answer must be a complete path from initiation to closure, not F alone.
Why the Week 6 method fits
The activities and durations are already supplied, so there is no need to invent a work breakdown structure or to re-estimate anything. Week 6’s activity-on-node networks, forward and backward passes, and float answer the two questions directly.
- Comparing the totals of the complete paths gives the answer quickly.
- The forward pass verifies when each activity can start.
- The backward pass and float explain why those activities are critical.
Key ideaShowing all three turns the submission into a worked analysis rather than an unsupported final number.
Given, and assumed
The brief gives the activities, their predecessors and their durations, and nothing else. Everything in the right-hand column below had to be assumed, and the submission states each assumption on its first page.
| Given by the brief | Assumed by the author |
|---|---|
| Seven activities, A to G | Every link is finish to start |
| Each activity’s predecessors | No leads or lags |
| Each activity’s duration in days | Durations are fixed |
| Two questions: the critical path and the duration | Enough resources for D and E to run at the same time |
| A two-page submission | Time starts at day 0, in relative schedule days, with no extra activities or contingency |
Applied choiceThese assumptions are the author’s, stated so a reader can see exactly which model was solved. Finish to start is the deck’s most common relationship, but the brief itself does not name a link type.
Key takeaways
- The brief asks for two results: the critical path and the total duration.
- The critical path is the longest complete chain of dependent activities; it sets the earliest finish.
- “Critical” is about the finish date, not about importance or difficulty.
- The brief gives activities, predecessors and durations; link types, resources and the time convention are assumptions.