Divergence after C, convergence at F
At C the network diverges into D and E. At F those branches converge again. Week 6 calls these path divergence and path convergence.
The route through D
- Start
- 2 daysAInitiation · first
- 4 daysBRequirements · after A
- 3 daysCDesign · after B
- 5 daysDPrototype · after C
- 6 daysFImplementation · after D and E
- 2 daysGClosure · after F
- End
The branch through E, beside D
- 4 daysETesting · after C, then F
C is the only predecessor of both D and E, so the network splits after C. F lists both D and E, so the two branches join again before implementation. Both branches are required work.
Why prototype development and testing can overlap
The brief lists C as the predecessor of both D and E. It does not list D as a predecessor of E. So, in this exercise, prototype development and testing may run at the same time. F needs both branches finished, and neither branch is optional.
Read with careIn many real projects, testing would follow prototype development. The guide says that inserting D before E here would change the problem: in real delivery you would validate that dependency with the team, but for this assignment the supplied table stands.
Two complete paths
Every route from initiation to closure passes through either D or E. The submission lists both complete paths and adds their durations.
| Complete dependency path | Duration calculation | Total |
|---|---|---|
| A → B → C → D → F → G | 2 + 4 + 3 + 5 + 6 + 2 | 22 days |
| A → B → C → E → F → G | 2 + 4 + 3 + 4 + 6 + 2 | 21 days |
Key ideaThe route through D is longer, so it governs completion of the whole project.
Concurrent paths, not alternatives
The submission adds a caution under its network: the two routes are concurrent dependency paths, not alternatives from which to choose. The 21-day route does not mean the project could finish in 21 days, because D is still required. Both branches remain part of the project.
The modelling choices behind the drawing
The network is drawn as activity on node, the representation Week 6 uses for its worked example. The links are finish to start, with no leads or lags, and the overlap of D and E assumes there are enough people to do both.
Applied choiceThe guide calls these stated assumptions, not extra facts provided by the brief. With a lead or a lag, or with one team that cannot do D and E together, the dates would change.
Key takeaways
- Read the predecessor column for splits and joins: C has two successors, F has two predecessors.
- D and E may overlap because the brief does not make E depend on D.
- The two complete paths take 22 and 21 days; the longer one governs.
- The paths run concurrently; neither branch is optional.