C splits, F joins: reading the network

The decisive detail is in the predecessor column. C is the only predecessor of both D and E, so the network splits after design; F needs both, so it joins again before implementation. That gives two complete paths, of 22 and 21 days.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Divergence after C, convergence at F

At C the network diverges into D and E. At F those branches converge again. Week 6 calls these path divergence and path convergence.

The assignment network · Redrawn from the Week 6 submission

The route through D

  1. Start
  2. Initiation · first
  3. Requirements · after A
  4. Design · after B
  5. Prototype · after C
  6. Implementation · after D and E
  7. Closure · after F
  8. End

The branch through E, beside D

  1. Testing · after C, then F

C is the only predecessor of both D and E, so the network splits after C. F lists both D and E, so the two branches join again before implementation. Both branches are required work.

Why prototype development and testing can overlap

The brief lists C as the predecessor of both D and E. It does not list D as a predecessor of E. So, in this exercise, prototype development and testing may run at the same time. F needs both branches finished, and neither branch is optional.

Read with careIn many real projects, testing would follow prototype development. The guide says that inserting D before E here would change the problem: in real delivery you would validate that dependency with the team, but for this assignment the supplied table stands.

Two complete paths

Every route from initiation to closure passes through either D or E. The submission lists both complete paths and adds their durations.

The two complete dependency paths · Submission p. 1
Complete dependency pathDuration calculationTotal
A → B → C → D → F → G2 + 4 + 3 + 5 + 6 + 222 days
A → B → C → E → F → G2 + 4 + 3 + 4 + 6 + 221 days

Key ideaThe route through D is longer, so it governs completion of the whole project.

Concurrent paths, not alternatives

The submission adds a caution under its network: the two routes are concurrent dependency paths, not alternatives from which to choose. The 21-day route does not mean the project could finish in 21 days, because D is still required. Both branches remain part of the project.

The modelling choices behind the drawing

The network is drawn as activity on node, the representation Week 6 uses for its worked example. The links are finish to start, with no leads or lags, and the overlap of D and E assumes there are enough people to do both.

Applied choiceThe guide calls these stated assumptions, not extra facts provided by the brief. With a lead or a lag, or with one team that cannot do D and E together, the dates would change.

Key takeaways

  • Read the predecessor column for splits and joins: C has two successors, F has two predecessors.
  • D and E may overlap because the brief does not make E depend on D.
  • The two complete paths take 22 and 21 days; the longer one governs.
  • The paths run concurrently; neither branch is optional.

Study explanation of an academic critical path submission and its study guide, read against the supplied Week 6: Scheduling course deck. Open the source notes above to see which document each claim comes from.