A schedule is built, not guessed
Read as a whole, the Week 6 deck treats a realistic schedule as the result of a chain of decisions. This page is a study-guide synthesis of the seven lessons and adds no new facts. In those terms, building a schedule means answering seven questions.
- How will we manage time Lesson 1 sets the schedule management plan before any schedule exists.
- What is the work Lesson 1 breaks the scope into a WBS of owned work packages and milestones.
- In what order Lesson 2 sequences the activities into a network diagram.
- Why that order Lesson 3 classifies the dependencies and adds leads and lags.
- How long Lesson 4 estimates each duration, from analogous to bottom up.
- On which dates Lesson 5 builds the schedule model and approves the baseline.
- What decides the finish, and how to recover Lessons 6 and 7 find the critical path and compress it when needed.
From management plan to a schedule you can defend
One way to hold the whole week in mind is as a chain, each step feeding the next. The chain loops: once execution starts, controlling the schedule may call for compression.
- Schedule management planMethod, tools, thresholds, reporting · Lesson 1
- Work breakdown structureOwned work packages and milestones · Lesson 1
- Network diagramPrecedence relationships and dependencies · Lessons 2 and 3
- Duration estimatesFrom analogous to bottom up · Lesson 4
- Schedule model and baselineCalendar based, approved, realistic, inclusive · Lesson 5
- Critical path and floatWhat governs the finish date · Lesson 6
- Control and compressFast track or crash when a date is at risk · Lesson 7
Quick reference
Use these four groups for revision. Each line links to the lesson section that teaches it.
Defining the work
- Schedule management plan
- Method, tools, baseline control, variance thresholds, reporting, iterations.
- Five steps
- Defining, sequencing, estimating, scheduling, controlling.
- Work package
- Lowest WBS level; two weeks or 80 hours at most; has an owner.
- Milestone
- A significant event with no duration, used to measure progress.
Sequencing and dependencies
- Finish to start
- The most common: the predecessor finishes before the successor starts.
- Mandatory or discretionary
- Hard logic from the work or a contract, or the organization’s preference.
- Lead and lag
- Start before the predecessor ends, or wait between activities.
- Convergence and divergence
- Two or more predecessors, or two or more successors.
Estimating and the schedule
- Analogous
- Top down from similar projects; rough, early, by sponsors.
- Bottom up
- Detailed estimates from the WBS, rolled up through control accounts.
- Baseline
- The approved schedule, changed only through change management.
- Four characteristics
- Calendar based, approved, realistic, inclusive.
Critical path and compression
- Total float
- LS − ES, or LF − EF; zero on the critical path.
- Forward and backward pass
- ES = largest predecessor EF; LF = smallest successor LS.
- Fast tracking
- Overlap critical activities; adds risk and rework.
- Crashing
- Add resources; always adds cost; crash the cheapest month first.