Management salaries: overhead or direct?Slide 12 lists “management salaries” among overhead costs, while slide 19 classifies the project manager’s salary as a direct cost. Slide 17 resolves it: head office and executive management are indirect. Lessons 1 and 2 say so.
Slipping, reversedThe notes on slide 68 say the project is slipping if earned value is above planned value. That contradicts the deck’s own formulas on slides 58-62, where SV above 0 and SPI above 1 mean ahead of schedule, and the status reading on slide 69. Lesson 6 follows the formulas: the project slips when EV is below PV.
Two formulas for earned valueSlide 57 gives EV as planned value times percent complete; slide 62 gives percent complete times the budget at completion. They agree only when the planned value is the work’s full budget, as in the slide 72 example, where the work was due to finish today. Lesson 5 uses the budget of the work.
ETC (t): time to completion, or final duration?Slide 62 labels planned duration ÷ SPI as the estimated time to completion, but its interpretation describes a prediction of the final project duration. Lesson 5 reports the interpretation.
Control does not only focus on costThe notes on slide 52 say project control “does only focus on cost but” also covers schedule, quality and resources. The sense is “does not only”, which Lesson 5 uses.
Contingency and escalation, promised laterSlide 13 says to always include contingency and escalation, “more on those later”, but the deck never returns to them. Lesson 1 reports the instruction without inventing a method.
The house exercise has no totalSlide 35 asks what else is needed to price the house; its notes answer with the wage rate and the exchange rate. Several quantities are ambiguous, such as whether areas are per floor, so Lesson 3 computes no total.
Diagram labels on slide 67The chart linking the earned value terms to the S-curves places its variance labels loosely. Lessons 5 and 6 rely on the formulas from slides 58 and 62 instead.
Overlapping engineering rangesThe AACE table on slide 39 gives project definition ranges that overlap from one class to the next: 1% to 15%, 10% to 40%, 30% to 70% and 50% to 100%. Lesson 4 reports them as printed.
Reported as statedSlide 31 lists “overall project costs will be capped” as an advantage of top-down estimation, and slide 61 gives EAC = BAC ÷ CPI as the only forecasting formula. Both are reported as the deck states them.
Study-guide calculationsThe deck stops at the indices in the slide 72 example. Lesson 6’s estimate at completion of 2,025 dollars and estimate to complete of 675 dollars apply the deck’s own slide 61 formulas and are labelled as calculations. Every deck calculation was rechecked, and all are correct.
Illustrative wordingTyping slips such as “one-time phased” (slide 12), “Bottoms Up” (slide 33), “project manger” (slide 19), “Tax rent” (slide 22) and “we have doing” (slide 69) are corrected without changing meaning.
Checked against the source slides cited in each note.