Planning & Controls · Project planningLesson 2

Study explanation · Lesson 02 · 9 min

The approved plan and the control loop

Connect planning, execution, feedback and corrective action, then distinguish the Charter, Scope Statement and Project Management Plan.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

Feedback must lead to a decision

Planning defines objectives, tasks and timelines. Execution mobilizes resources and performs the work. Feedback measures actual progress and deviations. Decisions adjust the plan, resources or priorities. The loop connects these activities so that the project remains aligned with its approved plan. Monitoring means watching performance. Control analyzes the gap and takes corrective action. A report that records a delay provides information; a decision about the response puts that information to use. The source's main distinction is that control requires decisions and action beyond reporting.

The planning and control loop in slide 4
  1. PlanObjectives, tasks and timelines
  2. ExecuteResources and work
  3. FeedbackProgress and deviations
  4. DecideAdjust and check again

Use the next cycle of feedback to check the effect of the decision.

The Management Plan explains how delivery will work

The Project Management Plan is the approved roadmap for execution, monitoring and control. It answers what, why, how, who, when and how much. The source groups these questions as scope, purpose, method, roles, schedule and budget. It also names schedule, budget, quality and risk as core subsidiary plans. The plan is developed collaboratively and formally approved before it guides the work. Collaboration brings relevant knowledge into the plan, while approval establishes the reference against which execution can be monitored and controlled. The source introduces these contents without supplying a complete plan template.

Core subsidiary plans in slide 5
PlanWhat it addresses
ScheduleWhen activities occur
BudgetHow costs are planned and controlled
QualityHow requirements and standards are met
RiskHow uncertainty is identified and managed

Authorization, scope definition and delivery planning have different jobs

The Project Charter authorizes the project and establishes purpose, high-level objectives, summary budget and milestones, and the project manager's authority. The Scope Statement defines the product description, deliverables, acceptance criteria, exclusions and constraints. The Management Plan explains the execution approach and how schedule, cost, quality, risk, communication, monitoring and control will be managed. Slide 6 places high-level approval before detailed definition and execution planning. Keep the three documents connected while retaining their separate purposes: permission to proceed, clarity about the work and a plan for delivering it.

The three documents compared in slide 6
DocumentMain purposeExamples of content
Project CharterAuthorizes the projectPurpose, high-level objectives, summary budget and milestones, PM authority
Scope StatementDefines the workProduct, deliverables, acceptance criteria, exclusions and constraints
Management PlanExplains deliveryExecution approach and the plans for managing and controlling work

Key takeaways

  • Monitoring observes performance; control analyzes gaps and acts.
  • Feedback connects execution with decisions.
  • The collaboratively developed Management Plan needs formal approval.
  • Charter, Scope Statement and Management Plan serve different purposes.

Based on Project_Planning_Summary (1).pptx by Farah Demachkieh, Ph.D.; slide references appear in the source notes and practice is a study-guide addition.