Feedback must lead to a decision
Planning defines objectives, tasks and timelines. Execution mobilizes resources and performs the work. Feedback measures actual progress and deviations. Decisions adjust the plan, resources or priorities. The loop connects these activities so that the project remains aligned with its approved plan. Monitoring means watching performance. Control analyzes the gap and takes corrective action. A report that records a delay provides information; a decision about the response puts that information to use. The source's main distinction is that control requires decisions and action beyond reporting.
- PlanObjectives, tasks and timelines
- ExecuteResources and work
- FeedbackProgress and deviations
- DecideAdjust and check again
Use the next cycle of feedback to check the effect of the decision.
The Management Plan explains how delivery will work
The Project Management Plan is the approved roadmap for execution, monitoring and control. It answers what, why, how, who, when and how much. The source groups these questions as scope, purpose, method, roles, schedule and budget. It also names schedule, budget, quality and risk as core subsidiary plans. The plan is developed collaboratively and formally approved before it guides the work. Collaboration brings relevant knowledge into the plan, while approval establishes the reference against which execution can be monitored and controlled. The source introduces these contents without supplying a complete plan template.
| Plan | What it addresses |
|---|---|
| Schedule | When activities occur |
| Budget | How costs are planned and controlled |
| Quality | How requirements and standards are met |
| Risk | How uncertainty is identified and managed |
Authorization, scope definition and delivery planning have different jobs
The Project Charter authorizes the project and establishes purpose, high-level objectives, summary budget and milestones, and the project manager's authority. The Scope Statement defines the product description, deliverables, acceptance criteria, exclusions and constraints. The Management Plan explains the execution approach and how schedule, cost, quality, risk, communication, monitoring and control will be managed. Slide 6 places high-level approval before detailed definition and execution planning. Keep the three documents connected while retaining their separate purposes: permission to proceed, clarity about the work and a plan for delivering it.
| Document | Main purpose | Examples of content |
|---|---|---|
| Project Charter | Authorizes the project | Purpose, high-level objectives, summary budget and milestones, PM authority |
| Scope Statement | Defines the work | Product, deliverables, acceptance criteria, exclusions and constraints |
| Management Plan | Explains delivery | Execution approach and the plans for managing and controlling work |
Key takeaways
- Monitoring observes performance; control analyzes gaps and acts.
- Feedback connects execution with decisions.
- The collaboratively developed Management Plan needs formal approval.
- Charter, Scope Statement and Management Plan serve different purposes.