Purpose, agreement and delivery
Projects are temporary, unique and progressively defined. The deck names Concept, Planning, Execution and Closeout as the four phases. Success balances scope, time, cost and client acceptance. The Charter authorizes, the Scope Statement defines the work, and the Management Plan explains how execution and control will work. Develop the plan collaboratively and secure formal approval.
Requirements become an approved scope reference
Collect stakeholder requirements, define inclusions and exclusions, and create the WBS. The RTM records an ID, requirement, source, status and owner. The WBS covers all agreed work through manageable work packages. Its Dictionary supplies element-level detail. The Scope Statement, WBS and Dictionary together form the scope baseline.
| Distinction | First concept | Second concept |
|---|---|---|
| Monitoring / control | Observe performance | Analyze gaps and take corrective action |
| Verification / quality | Completeness and formal acceptance | Correctness and quality standards |
| WBS / Dictionary | Hierarchy of approved work | Details for each element |
Keep the control loop active
Plan, execute, collect feedback and decide. Verify agreed delivery and check quality using their different criteria. For a change, describe the request, assess impact, obtain an approval or rejection and update the affected baselines for approved changes. Planning early, breaking down work and controlling additions help keep delivery aligned with the agreement.