Build the WBS and establish the scope baseline

Break agreed scope into manageable work packages and connect the Scope Statement, WBS and WBS Dictionary into an approved reference.

Listen to this lesson

Hear the lesson read aloud, with each sentence highlighted as you go.

Narrated by an AI voice.

A hierarchy makes the full scope manageable

The Work Breakdown Structure turns the project scope into manageable work. Slide 9 illustrates a project divided into Design, Procurement, Construction and Handover. Beneath these branches are plans and permits, vendors and long-lead items, foundation and structure, and testing and training. The hierarchy organizes the work before detailed schedules and resource decisions are made. The 100% rule in this deck means all agreed work and no extra work. A missing branch leaves required work unplanned. An extra branch can introduce work outside the agreement. The WBS should therefore be checked against the defined deliverables and boundaries.

The illustrative WBS in slide 9
Project branchWork shown beneath it
DesignPlans; permits
ProcurementVendors; long-lead items
ConstructionFoundation; structure
HandoverTesting; training

A work package needs enough detail to manage

The deck calls the work package the lowest WBS level. It specifies a clear deliverable, one owner, duration, budget, resources and measurable milestones. These details make it possible to plan and monitor that part of the result. A label such as Handover becomes useful only when its work is described clearly enough for someone to own and deliver it. This source states the attributes to capture; it supplies no complete worked work-package estimate or dictionary template. When creating a study example, keep invented durations, resource quantities and budgets visibly separate from the source's actual data.

  • A clear deliverable and one owner.
  • Duration, budget and required resources.
  • Milestones that allow progress to be measured.

Three approved components form the scope baseline

The scope baseline consists of the Scope Statement, WBS and WBS Dictionary. The Scope Statement holds boundaries, deliverables, acceptance criteria, assumptions and constraints. The WBS is the hierarchical breakdown of the approved scope. The Dictionary supplies the owner, time, cost, resources and description for each WBS element. Approval makes this combination the reference for assessing a proposed change. The hierarchy shows where work belongs; the dictionary explains its details. A proposed change should be measured against the whole agreed baseline, rather than judged solely by whether someone can fit another task into the current week.

The scope baseline in slide 10
  1. Scope StatementDetailed boundaries and acceptance
  2. WBSHierarchy of total approved work
  3. WBS DictionaryDetails for each element
  4. Scope baselineApproved reference for change

Key takeaways

  • The WBS organizes the full agreed scope.
  • A work package is the lowest WBS level in this deck.
  • The Dictionary adds the detail needed to manage each element.
  • The scope baseline combines the approved Statement, WBS and Dictionary.

Based on Project_Planning_Summary (1).pptx by Farah Demachkieh, Ph.D.; slide references appear in the source notes and practice is a study-guide addition.