Scope management begins with needs and ends with controlled change
The deck gives five steps: collect requirements, define scope, create the WBS, verify scope and control scope. Requirements ask what stakeholders need. Scope definition decides what is included and excluded. The WBS breaks down the work. Verification asks whether the agreed work was delivered. Control decides how changes will be managed. The stated goal is to include all work required, and only work required, to achieve the objectives. Clear boundaries help the team recognize an omission and an unapproved addition. They also give later verification and change decisions a shared reference.
- Collect requirementsWhat do stakeholders need?
- Define scopeWhat is included and excluded?
- Create WBSHow will work be broken down?
- Verify scopeWas the agreed work delivered?
- Control scopeHow will changes be managed?
Different collection methods reveal different information
Slide 8 names interviews, focus groups, workshops, questionnaires and surveys, observation, and prototypes as ways to collect requirements. They are means of learning what stakeholders need before that need becomes an agreed scope commitment. The source names the methods without prescribing one mandatory method for every project. Study-guide example: a workshop can bring a client and delivery team together to clarify an unclear request; a prototype can give them something concrete to discuss. The appropriate method depends on the information needed. These applications illustrate the named methods rather than add a procedure from the deck.
- Interviews, focus groups and workshops.
- Questionnaires and surveys.
- Observation and prototypes.
Trace each requirement to a source, an owner and a status
The Requirements Traceability Matrix shown in the deck contains an ID, requirement, source, status and owner. Its purpose is to make the requirement traceable and give the team a clear view of who follows it and where it stands. The three examples include a Charter requirement, an IT standard and a Contract requirement. A status such as Open, Done or Active records the requirement's state in the example. It does not replace the acceptance criteria or prove that the full project scope has been formally accepted. The table makes responsibility and origin visible so the team can investigate and follow through.
| ID | Requirement | Source | Status | Owner |
|---|---|---|---|---|
| R-01 | Emergency exit signage | Charter | Open | Design |
| R-02 | 4 GB laptop memory | IT standard | Done | Procurement |
| R-03 | Weekly client report | Contract | Active | PM |
Key takeaways
- Collect needs before deciding scope boundaries.
- The source names six families of requirement-collection methods.
- An RTM identifies a requirement's source, owner and status.
- Verification and change control follow the agreed definition of the work.