Original source guide

Week 6: Scheduling

This map preserves the deck’s teaching sequence while the lessons provide a clearer, learner-facing explanation. Use it to trace every study topic back to the supplied source.

How to use this page

The source is the Week 6 course deck by Dr. Daoud Kiomjian, American University of Beirut. Open a lesson source note for its original teaching focus and slide range. Slide numbers are PDF page numbers, because the deck’s speaker notes run onto extra pages. The deck itself is not republished here, and its diagrams are redrawn rather than copied; distribute the original PDF only when you hold the necessary rights.

Study-guide syntheses

Four elements connect the deck’s ideas rather than quoting it: the arrangement of estimation methods in Lesson 4, the free float column and path lengths in Lesson 6, the fast-tracking bars in Lesson 7, and the Week 6 summary. Each is labelled and adds no new facts. Open the Week 6 summary

Lesson 01

Scheduling basics

A schedule starts with a plan for managing it and a breakdown of the work. This lesson covers the schedule management plan, the five-step scheduling process, the work breakdown structure, work packages, milestones, and rolling wave planning.

Open learner explanation
Some background

Time as a key success factor; most capital projects slip; schedules must be realistic.

Source slides 5-6
The schedule management plan

Methodology, tools, baseline control, variance thresholds, reporting, and iterations.

Source slides 7-8
Scheduling projects: a process

Defining, sequencing, estimating, scheduling, and controlling.

Source slides 9-10
Planning vs scheduling

Sequential planning and scheduling; parallel planning and costing.

Source slides 11-12
Defining activities: work breakdown

By area, components, or trade; the link to costing; where to stop.

Source slides 13-16
WBS and work packages

The WBS as a visual hierarchy; work packages of 80 hours or less with owners; four guidelines.

Source slides 17-22
Milestones

Significant events with no duration, used to measure progress.

Source slides 23-24
WBS examples

An outline WBS by zones and a graphic WBS for an event.

Source slides 25-27
Agile and rolling wave planning

Progressive elaboration within a known scope.

Source slides 28-29

Lesson 02

Activity sequencing

With the activities defined, the next step is their order. Sequencing sets the precedence relationships between activities and produces a network diagram, drawn either with activities on nodes or on arcs, and linked finish to start, start to start, or finish to finish.

Open learner explanation
Sequencing: some recap

Objectives, scope, WBS, and sequence; good schedules start at definition.

Source slides 31-32
Sequencing activities

Precedence relationships and the activity-on-node network diagram.

Source slides 33-34
Activity on arc

Arcs as activities, nodes as start and finish events.

Source slides 35-36
Which activities start immediately

Activities with no predecessors start at once.

Source slide 37
Finish to start

Most common; dig the hole, then plant the tree.

Source slides 38-39
Start to start

Design and code; tubing and wiring.

Source slide 40
Finish to finish

Testing and documentation; commissioning and as-builts.

Source slide 41

Lesson 03

Dependencies

The precedence relationship between two activities depends on the type of dependency between them. Dependencies are mandatory or discretionary by logic, and internal or external by the party requesting them; leads and lags fine-tune the links, and the result is a well-formed network diagram.

Open learner explanation
Types of dependencies

By logic and by party; not mutually exclusive.

Source slides 43-44
Logical dependencies

Mandatory (hard logic) and discretionary (soft logic) dependencies.

Source slides 45-46
Dependencies by party

External (government, suppliers) and internal dependencies.

Source slides 47-48
Leads and lags

Starting early and waiting between activities.

Source slides 49-50
The network diagram

Good practices, convergence, divergence, and software.

Source slides 51-53

Lesson 04

Activity estimation

The goal of scheduling is the project’s duration, so each activity needs a duration estimate. The deck covers relative sizing, one-point estimates, parametric estimation, analogous top-down estimates, and bottom-up estimates built from the WBS.

Open learner explanation
Estimating activities

Durations as the goal; uncertainty and probability.

Source slide 55
Relative sizing and one-point estimates

Story points on adaptive projects; one figure from history or expertise.

Source slides 56-57
Parametric estimation

Regression, learning curves, and heuristics.

Source slide 58
Analogous estimation

Top-down estimates from similar projects, by sponsors.

Source slides 59-60
Bottom-up estimation

Detailed estimates rolled up through control accounts.

Source slides 61-62

Lesson 05

Preparing the schedule

With activities listed and estimated, the schedule model can be built. Once approved it becomes the baseline. A good schedule is calendar based, approved, realistic, and inclusive, and it draws on a long list of inputs, from scope to the risk register.

Open learner explanation
Preparing the schedule

The schedule model, bar charts, milestone lists, and the baseline.

Source slides 64-65
Characteristics of the schedule

Calendar based, approved, realistic, and inclusive.

Source slides 66-67
A long list of inputs

Scope, activities, milestones, dependencies, basis, resources, and history.

Source slide 68
What else do we need

Resource calendars, RBS, company calendar, team assignments, and the risk register.

Source slides 69-70

Lesson 06

The critical path method

The critical path method finds the longest path through the network, which governs the project’s duration. A forward pass gives each activity’s early dates, a backward pass its late dates, and their difference is float. The deck works one example through from start to finish.

Open learner explanation
The critical path method

Longest path, early and late dates, and the critical activity list.

Source slides 72-73
The concept of float

Total, free, project, and negative float.

Source slides 74-75
Linking float to the critical path

Zero float, negative float, near-critical activities, and float as an asset.

Source slides 76-77
Notation and formulas

The node layout and the float formulas.

Source slides 78-79
Learning through an example

Eight activities and their dependencies.

Source slide 80
The forward and backward passes

Early dates, late dates, and the 26-day finish.

Source slides 81-84
Float calculations

Critical path D, E, G, H, C; floats of 2, 1, and 10.

Source slide 85

Lesson 07

Schedule compression

When a schedule constraint cannot be met as things stand, the schedule can be compressed. Fast tracking overlaps critical activities and adds risk; crashing adds resources and always adds cost. The deck works through both and compares them with reducing scope and cutting quality.

Open learner explanation
Schedule compression

Unrealistic estimates or late projects; manage differently, keep the baseline.

Source slide 87
Fast tracking

Parallel critical activities, rework, risk, and communication.

Source slide 88
What activities would you fast track

H with G, and part of C with H, if dependencies are discretionary.

Source slide 89
Schedule crashing

Adding resources, always at a cost.

Source slide 90
Crashing example

Crash J and N for 5,000 dollars to recover three months.

Source slide 91
Compression methods compared

Fast track, crash, reduce scope, and cut quality.

Source slide 92

Source appendix

Where the deck needs a careful reading

Read with care

A leftover Week 5 slide

Lesson 1 opens on slide 3 with “Types of Integrated Project Teams”, and its notes repeat the Week 5 point that projects are as strong as the people doing them. It belongs to Week 5, so the scheduling lessons leave it out.

Does fast tracking always add risk?

Slide 88 says fast tracking “usually increases risk”; the comparison table on slide 92 says it “always adds risk”. Lesson 7 shows both.

Rolling wave planning and a closed scope

Slides 28-29 let activities be detailed and added as iterations progress, yet say the scope must be known before the project starts; the notes say it must be closed. Lesson 1 reads them together: the activities grow, the scope boundary does not.

Top-down WBS, bottom-up estimates

Slide 21 says to build the WBS top down; slide 61 describes bottom-up estimation. They are different steps, since bottom-up estimation starts from the finished WBS’s lowest level. Lesson 4 says so.

The start-to-start example

The notes on slide 40 say “we cant start with coding before designing the product”, which reads like finish to start. The slide’s definition, and its tubing and wiring example, need only the predecessor to have started. Lesson 2 follows the definition.

Slips in the backward pass

The notes on slide 83 give C’s late start as “26 minus 7 which is 7”; the diagram shows 19, which is correct. The notes on slide 84 say F can finish without delaying its predecessors, where successors is meant, and “backward bass” means backward pass. Lesson 6 uses the diagram’s numbers.

Two lead examples

Slide 49 starts web design five days before the database is completed; its notes start construction five days before design is finalized. Lesson 3 shows both.

Fixed early, yet dynamic

Slide 7 says the schedule management approach is decided firmly early, “cast in stone”; slide 69 says schedules are dynamic and iterative. The first is the approach, the second the schedule, whose approved baseline changes only through change management (slide 64). Lessons 1 and 5 keep them apart.

Statistics that never arrive

Slide 55 says estimating needs some statistics first, but none follow, and slide 61 names three-point estimates without a formula. Lesson 4 adds no formula of its own.

Terms reported as drawn

Slide 59 says analogous estimates are done by project sponsors, and slide 74 says project float is also called positive float. Both are reported as the deck states them.

Study-guide calculations

The deck computes total float only. Lesson 6’s free float column and its list of path lengths apply the deck’s own formulas and numbers from slides 79-85; they are labelled as calculations, not source content.

Illustrative wording

Typing slips such as “ensure that is a project in time” (slide 5), “creased costs” (slide 90), “Origin Duration” (slide 91), and a stray “events” (slide 66) are corrected without changing meaning.

Checked against the source slides cited in each note.

What not to take away

The lessons actively work against these misreadings of the material:

  • A schedule can be built before deciding how it will be managed.
  • Planning and scheduling are the same task.
  • Every small purchase deserves its own line in the WBS.
  • A milestone is a short activity.
  • Rolling wave planning means the scope can stay open.
  • Start to start means the predecessor must finish first.
  • Every dependency in a schedule is mandatory.
  • A lead and a lag are the same thing.
  • Analogous estimates are as accurate as bottom-up ones.
  • A baseline can be changed whenever the dates move.
  • Only activities on the critical path need watching.
  • Total float and free float are always equal.
  • Fast tracking is free.
  • Crashing is cheapest when you crash the longest activity.

Study-guide synthesis; each item is addressed in the lessons.