A leftover Week 5 slideLesson 1 opens on slide 3 with “Types of Integrated Project Teams”, and its notes repeat the Week 5 point that projects are as strong as the people doing them. It belongs to Week 5, so the scheduling lessons leave it out.
Does fast tracking always add risk?Slide 88 says fast tracking “usually increases risk”; the comparison table on slide 92 says it “always adds risk”. Lesson 7 shows both.
Rolling wave planning and a closed scopeSlides 28-29 let activities be detailed and added as iterations progress, yet say the scope must be known before the project starts; the notes say it must be closed. Lesson 1 reads them together: the activities grow, the scope boundary does not.
Top-down WBS, bottom-up estimatesSlide 21 says to build the WBS top down; slide 61 describes bottom-up estimation. They are different steps, since bottom-up estimation starts from the finished WBS’s lowest level. Lesson 4 says so.
The start-to-start exampleThe notes on slide 40 say “we cant start with coding before designing the product”, which reads like finish to start. The slide’s definition, and its tubing and wiring example, need only the predecessor to have started. Lesson 2 follows the definition.
Slips in the backward passThe notes on slide 83 give C’s late start as “26 minus 7 which is 7”; the diagram shows 19, which is correct. The notes on slide 84 say F can finish without delaying its predecessors, where successors is meant, and “backward bass” means backward pass. Lesson 6 uses the diagram’s numbers.
Two lead examplesSlide 49 starts web design five days before the database is completed; its notes start construction five days before design is finalized. Lesson 3 shows both.
Fixed early, yet dynamicSlide 7 says the schedule management approach is decided firmly early, “cast in stone”; slide 69 says schedules are dynamic and iterative. The first is the approach, the second the schedule, whose approved baseline changes only through change management (slide 64). Lessons 1 and 5 keep them apart.
Statistics that never arriveSlide 55 says estimating needs some statistics first, but none follow, and slide 61 names three-point estimates without a formula. Lesson 4 adds no formula of its own.
Terms reported as drawnSlide 59 says analogous estimates are done by project sponsors, and slide 74 says project float is also called positive float. Both are reported as the deck states them.
Study-guide calculationsThe deck computes total float only. Lesson 6’s free float column and its list of path lengths apply the deck’s own formulas and numbers from slides 79-85; they are labelled as calculations, not source content.
Illustrative wordingTyping slips such as “ensure that is a project in time” (slide 5), “creased costs” (slide 90), “Origin Duration” (slide 91), and a stray “events” (slide 66) are corrected without changing meaning.
Checked against the source slides cited in each note.